Chapter 12, Problem 27P

(a):

To determine

Calculate the internal rate of return.

(a):

Expert Solution
Check Mark

Explanation of Solution

The initial investment (IN) is $750,000. Net income (NY) is $135,000 per year. Time period (n) is 10. MARR (i) is 12%.

The internal rate of return (ir) can be calculated using the following formula:

IN=NY((1+ir)n1ir(1+ir)n)750,000=135,000((1+ir)n1ir(1+ir)n)((1+ir)101ir(1+ir)10)=750,000135,000((1+ir)101ir(1+ir)10)=5.5556

Substitute ir as 0.12 by trial and error method in the above calculation.   

((1+0.12)1010.12(1+0.12)10)=5.5556(3.105810.12(3.1058))=5.5556(2.10580.3727)=5.55565.6501>5.5556

The calculated value is less than the present value factor to the annual value. Thus, increase the ir value to 0.124.

((1+0.124)1010.124(1+0.124)10)=5.5556(3.218910.124(3.2189))=5.5556(2.21890.3991)=5.55565.55985.5556

Since the calculated value is equal to the present value factor to the annual value, the value of ir is confirmed as 12.4%.

The value PI can be calculated as follows:

PI=NY((1+i)n1i(1+i)n)IN=135,000((1+0.12)1010.12(1+0.12)10)750,000=135,000(3.105810.12(3.1058))750,000=135,000(2.10580.3727)750,000=135,000(5.6501)750,000=1.02

The value of PI is 1.02.

The value PW can be calculated as follows:

PW=IN+NY((1+i)n1i(1+i)n)=750,000+135,000((1+0.12)1010.12(1+0.12)10)=750,000+135,000(3.105810.12(3.1058))=750,000+135,000(2.10580.3727)=750,000+135,000(5.6501)=750,000+762,763.5=12,763.5

The present wroth (PW) is $12,763.5.

(b):

To determine

The measures for which the project is economically justified.

(b):

Expert Solution
Check Mark

Explanation of Solution

The internal rate of return is greater than MARR. PI is greater than 1 and the present worth is greater than 0. Thus, the project is economically justified by these three measures.

(c):

To determine

Calculate the breakeven rate of interest.

(c):

Expert Solution
Check Mark

Explanation of Solution

The breakeven interest rate can be calculated using the following spreadsheet function:

= RATE(10,135000,-750000)

The above function gives the value of 12.4148%. Thus, the breakeven interest rate is 12.4148%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
2. a) Consider a market where one firm (firm 1) currently produces, but a second firm (firm 2) is intending to enter and sell an identical product. The market has inverse demand given by p = 40 – Q, where Q is the total output sold in the market. Firm 1 has a marginal cost of 16 and firm 2 has a marginal cost of c < 16, with no fixed cost for either firm. Firm 2 has a choice of competing on price or quantity, with firms making their choices simultaneously (i.e. the market will be either a Bertrand or Cournot duopoly). If you were advising firm 2 on entering this market, how would you advise it to compete? To what extent would the size of firm 2’s cost advantage affect your advice?  b) Now assume that firm 2 is aware that other firms are considering entering the market, so the market may over time change from a duopoly to an oligopoly with more than two firms. This would not change the nature of competition (i.e. any additional firms would set price or quantity in line with the first…
1. Consider two firms (i=1,2) interacting in the market. Assume that firms compete in quantities and therefore they choose either to cooperate or not in each round. If a firm deviates it earns monopoly profit for a round and a punishment phase will follow from next round onwards (for ever) where both firms choose the Cournot quantity. Assume a discounting factor & and that firms meet in the market in every period. The demand facing the industry is p = 1 92. Let Q = q1 + 92 denote the aggregate industry output - 91 - level. Assume further that production is costless.
Q4 (30 points) Subsidy in Auctions Consider a sealed-bid second-price auction with two bidders. Valuation of bidder 1 is drawn from the uniform distribution on [0, 100], and valuation of bidder 2 is independently drawn from the uniform distribution on [0, 300].
Knowledge Booster
Background pattern image
Economics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education
DATA GEMS: How to Access Income Data Tables and Reports From the CPS ASEC; Author: U.S. Census Bureau;https://www.youtube.com/watch?v=BWpVC-Clczw;License: Standard Youtube License