Select the alternative.
Explanation of Solution
Time period is denoted by n and the interest is denoted by i. Equivalent annual cost (EUAC) of alternate nothing can be calculated as follows.
Equivalent annual cost of alternate nothing is $10,000.
Increasing rate is denoted by f. Equivalent annual cost (EUAC) of alternate culvert can be calculated as follows.
Equivalent annual cost of alternate culvert is $7,688. The equivalent annual cost is lower for the alternate culvert. Thus, select alternate culvert.
Want to see more full solutions like this?
Chapter 12 Solutions
Engineering Economy (16th Edition) - Standalone book
- In preparing for the upcoming holiday season, Fresh Toy Company (FTC) designed a new doll called The Dougie that teaches children how to dance. The fixed cost to produce the doll is $100,000. The variable cost, which includes material, labor, and shipping costs, is $34 per doll. During the holiday selling season, FTC will sell the dolls for $42 each. If FTC overproduces the dolls, the excess dolls will be sold in January through a distributor who has agreed to pay FTC $10 per doll. Demand for new toys during the holiday selling season is extremely uncertain. Forecasts are for expected sales of 60,000 dolls with a standard deviation of 15,000. The normal probability distribution is assumed to be a good description of the demand. FTC has tentatively decided to produce 60,000 units (the same as average demand), but it wants to conduct an analysis regarding this production quantity before finalizing the decision. (a) Create a what-if spreadsheet model using a formula that relates the…arrow_forwardSunshine Smoothies Company (SSC) manufactures and distributes smoothies. It is considering the "weight loss" smoothies project. The project would require a $4 million investment outlay today The after-tax cash flows would depend on consumers’ demand. There is a 30% chance that demand will be good, and the project will produce after-tax cash flows of $2 million at the end of each year for the next 3 years. There is a 70% chance that demand will be poor, and the project will produce after-tax cash flows of $1 million at the end of each year for the next 3 years. The project is riskier than the firm's other projects, so it has a WACC of 12%. - The firm will know whether the project is success or not after receiving first year's cash flows from normal operating.. - After receiving the first year's cash flows (no matter what receive $1M or $2M in the first year), the firm will have the option to abandon the project. - If the firm decides to abandon the project, the company will no longer…arrow_forwardThe economically destructive price spike of 2007–2008 occurred when spare production capacity fell below 1 mbpd, causing a run-up in oil price from $50 to $145 per barrel. An issue for world oil spare capacity is the internal consumption of OPEC producers. OPEC production has ranged between 30 and 33 mbpd since 2004. Internal use is currently about 25% of total OPEC production, but it is growing by 2% per year. The internal consumption growth is largely for nonelastic end uses such as electricity generation, water treatment, and new buildings. If the current world spare capacity is 2 mbpd and the OPEC total production does not increase beyond 33 mbpd, how many years will it take for the spare capacity to fall below 1 mbpd again?arrow_forward
- Gerry should get a new car every (enter your response) here years, which has the (highest/lowest) EAC of (enter your response)$arrow_forwardThe government of a subtropical country is evaluating the costs and benefits of protecting a rainforest versus cutting it down for timber. The estimated value of the wood is $270$270 million. If the same forest is used as a national park, it may attract 0.030.03 million additional tourists per year. Statistically, each tourist spends $1,600$1,600 inside the country during their stay.How long will it take tourism to exceed the estimated value of the wood in the rainforest? Enter your answer in the box below and round to two decimal places if necessary.arrow_forwardFethe's Funny Hats is considering selling trademarked, orange-haired curly wigs for University of Tennessee football games. The purchase cost for a 2-year franchise to sell the wigs is $20,000. If demand is good (40% probability), then the net cash flows will be $27,000 per year for 2 years. If demand is bad (60% probability), then the net cash flows will be $9,000 per year for 2 years. Fethe's cost of capital is 14%. A. What is the expected NPV of the project? B. Use decision-tree analysis to calculate the expected NPV of this project, including the option to continue for an additional 2 years. B. Use decision-tree analysis to calculate the expected NPV of this project, including the option to continue for an additional 2 years.arrow_forward
- ANSWER WHAT IS ASKED ON THE PROBLEM AND WRITE YOUR SOLUTION CLEARLY ON A CLEAN PAPER. BOX YOUR FINAL ANSWERarrow_forwardPlease show work on Excel. A new engineer is evaluating whether to use a larger diameter pipe for a water line. The pipe will cost $327,089 more initially but will reduce pumping costs. The optimistic, most likely, and pessimistic projections for annual savings are $30,000, $20,000, and $5000, with respective probabilities of 20%, 50%, and 30%. The interest rate is most likely to be 7%, but is equally likely to be 6% or 8%, and the water line should have a life of 40 years. Find the expected annual savings and the expected interest rate. Determine the Expected PW based on these. Hint: Based on the different saving and their probabilities, find the expected value of savings. Then find the expected value of the interest rate (each option has equal probability). Then find the PW using these values.arrow_forwardConstruction on your custom home is complete and now the yard must be landscaped. The landscape contractor has estimated that 8 cubic yards of dirt and 3 cubic yards of sand will be required to level the yard and provide proper drainage. Dirt is priced at $35 per cubic yard and sand is priced at $27 per cubic yard. She has measured the yard and calculated the area needing sod to be 3600 ft2. Sod is sold in rolls that measure 90 ft? at a cost of $10 each per roll. Shrubbery installation will cost an additional $2500. Estimate the cost of the landscaping.arrow_forward
- An automobile spare part is sold for $15 per unit. The VC are $3 per unit, 15000 units of the product are sold annually and a profit of $80,000 is made. The change to be made in the design of the product will increase the VC by 20% and the FC by 10%, and the sales amount will increase to 18000 units. a) At what selling price do we break even? b) What is the annual profit when the selling price remains the same ($12/unit)?arrow_forwardYou and your friends have decided to build a skateboard ramp behind your house. You have already purchased $500 in materials and are considering renting an electric saw.It costs $20/hr to rent an electric saw. You estimate it will take 6 hours to build the ramp. If you decide to use your saw, which is a handsaw, you will not have to pay anything to rent an electric saw, but it will take 15 hours to build the ramp. Regardless of the decision, you will need to ask for time off from your job, which pays $8/ hour.arrow_forwardYou are requested to pick an implementation technology for your embedded product to maximize the profit. You have a competitor that will release a similar product 25 weeks from today. If the maximum expected product lifetime in the market is 50 weeks and the projected maximum number of sold units/week by the market leader is 1M units. Assume that the price is constant throughout the product lifetime ($50 USD). 'The available implementation technologies are: T1 T2 T3 NRE cost Unit cost (material and manufacturing) 100 USD Time to market 100K USD 1M USD 10M USD 5 USD 40 weeks 25 USD | 20 weeks 30 weeks a) What is the maximum revenue that might be generated for this product? b) Assuming no competition and ignoring the given max number of sold units/week, what is the max number of units sold per week to achieve the same profit from T1 and T3? Assume no competition. c) With the competition, what is the maximum profit that might be achieved if you go with T1? d) With the competition, what is…arrow_forward
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education