Using the accompanying diagram, do the following:
a. Draw a tree diagram for the scissors.
b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note: There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.
Use lot-for-lot ordering for all items.
a)

To prepare: Tree diagram for the scissors.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.
In addition to that, following diagram is given:
Prepare tree diagram for the scissors using given diagram:
b)

To prepare: A Material requirement planning for scissors.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.
In addition to that, following diagram is given:
Develop material requirement planning for scissors:
- It is given that 600 pairs of scissors are needed on day 6.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 6 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 6. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
Develop material requirement planning for bottom blade assembly:
- Scissor is the parent for bottom blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the bottom blade assembly. As number of units required is 1 for bottom blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of bottom blade assembly.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5(600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop material requirement planning for top blade assembly:
- Scissor is the parent for top blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the top blade assembly. As number of units required is 1 for top blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of top blade assembly.
- Beginning inventory is 40 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 5 (600-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 5. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
- Projected on hand inventory for week 6 is 0 units. Calculation is as follows:
Develop material requirement planning for screw:
- Scissor is the parent for screw. Hence, the planned order release of the scissor would be the gross requirement of the screw. As number of units required is 1 for screw, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of screw.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop material requirement planning for straight blade:
- Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
- Beginning inventory is 200 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 400 units in week 4(600-200).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 400 units in the beginning of Week 4. Hence, they need to order for 400 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop material requirement planning for straight plastic grip:
- Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 4 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. Company requires 600 units in the beginning of Week 4. Hence, they need to order for 600 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
Develop material requirement planning for bent blade:
- Top blade assembly is the parent for bent blade. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent blade. As number of units required is 1 for bent blade, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent blade.
- Beginning inventory is 350 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 210 units in week 4 (560-350).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 210 units in the beginning of Week 4. Hence, they need to order for 210 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop material requirement planning for bent plastic grip:
- Top blade assembly is the parent for bent plastic grip. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent plastic grip. As number of units required is 1 for bent plastic grip, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent plastic grip.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 4 (560-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 4. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3
Want to see more full solutions like this?
Chapter 12 Solutions
OPERATIONS MANAGEMENT(LL)-W/CONNECT
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Principles Of Taxation For Business And Investment Planning 2020 Edition
FUNDAMENTALS OF CORPORATE FINANCE
Financial Accounting, Student Value Edition (5th Edition)
- Do you feel there is anything positive about rework?arrow_forwardDo you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forward
- Have you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forwardResearch a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forward
- Do you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forwardGiven the significant impact on finances, production timelines, and even equipment functionality, as you pointed out, what do you believe is the most effective single strategy a company can implement to significantly reduce the occurrence of rework within their operations?arrow_forwardDurban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…arrow_forward
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardDurban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…arrow_forwardRead the project statement and answer ALL of the questions that follow PROJECT STATEMENT The African Integrated High-Speed Railway Network (AIHSRN). African nations are preparing to invest billions in a significant overhaul of their rail infrastructure as part of an ambitious plan for the continent. One of the key projects underway is the African Integrated High-Speed Railway Network (AIHSRN), which aims to connect Africa's capital cities and major commercial centres with a high-speed railway network to enhance continental trade and competition. This network will span 2,000 km (1,243 miles) and connect 60 cities, including Nairobi, Lagos, Cairo, and Dakar. It will improve access to essential markets, enhance economic cooperation, and encourage regional collaboration. The plan is poised to revolutionise intra-African trade by reducing travel times and lowering transportation costs, making trade between African nations more competitive. The trains will be capable of reaching speeds of up…arrow_forward
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning