OPERATIONS MANAGEMENT(LL)-W/CONNECT
OPERATIONS MANAGEMENT(LL)-W/CONNECT
13th Edition
ISBN: 9781260676310
Author: Stevenson
Publisher: MCG
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 12, Problem 12P

A firm that produces electric golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times, and quantities on hand is shown in the following table. Use this information to do each of the following:

a. Construct a product tree.

b. Construct an assembly time chart.

c. Develop a material requirements plan that will provide 200 golf carts by week 8 assuming lot-for-lot ordering.

Chapter 12, Problem 12P, A firm that produces electric golf carts has just received an order for 200 carts, which must be

a)

Expert Solution
Check Mark
Summary Introduction

To construct: A product tree

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  1

Construct a product tree:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  2

b)

Expert Solution
Check Mark
Summary Introduction

To construct: An assembly time chart

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  3

Construct an assembly time chart:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  4

c)

Expert Solution
Check Mark
Summary Introduction

To prepare: Materials Requirement planning using the provided information.

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).

Explanation of Solution

Given information:

The company needs to provide 200 golf carts by week 8.

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  5

Develop a material requirement planning for golf cart:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  6

  • It is given that the company needs to provide 200 golf carts by week 8.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 200 units in week 8 (200-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 200 units in the beginning of Week 8. Hence, they need to order for 200 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 7.

Develop a material requirement planning for top:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  7

  • Golf cart is the parent for top. Hence, the planned order release of the golf cart would be the gross requirement of the top. As number of units required is 1 for top, the planned order release row of golf cart should be multiplied with 1 to attain the gross requirement column of top.
  • Beginning inventory is 40 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units in week 7 (200-40).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 160 units in the beginning of Week 7. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 6.
  • Projected on hand inventory for week 8 is 0 units. Calculation is as follows:

Projected on hand for Week 8={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(40+160200)+0=0

Develop a material requirement planning for supports (4):

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  8

  • Top is the parent for supports. Hence, the planned order release of the top would be the gross requirement of the supports. As number of units required is 4 for supports, the planned order release row of top should be multiplied with 4 to attain the gross requirement column of support.
  • Beginning inventory is 200 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 440 units in week 6 (640-200).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 440 units in the beginning of Week 6. Hence, they need to order for 440 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
  • Projected on hand inventory for week 7 is 0 units. Calculation is as follows:

Projected on hand for Week7={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(200+440640)+0=0

Develop a material requirement planning for cover:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  9

  • Top is the parent for cover. Hence, the planned order release of the top would be the gross requirement of the cover. As number of units required is 1 for cover, the planned order release row of top should be multiplied with 1 to attain the gross requirement column of cover.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units in week 6 (160-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 160 units in the beginning of Week 6. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.

Develop a material requirement planning for base:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  10

  • Golf cart is the parent for base. Hence, the planned order release of the golf cart would be the gross requirement of the base. As number of units required is 1 for base, the planned order release row of golf cart should be multiplied with 1 to attain the gross requirement column of base.
  • Beginning inventory is 20 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units in week 7 (200-20).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 180 units in the beginning of Week 7. Hence, they need to order for 180 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 6.
  • Projected on hand inventory for week 8 is 0 units. Calculation is as follows:

Projected on hand for Week 8={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(20+180200)+0=0

Develop a material requirement planning for motor:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  11

  • Base is the parent for motor. Hence, the planned order release of the base would be the gross requirement of the motor. As number of units required is 1 for motor, the planned order release row of base should be multiplied with 1 to attain the gross requirement column of motor.
  • Beginning inventory is 300 units.
  • Gross requirement for week 6 is 180 units. As the beginning inventory is sufficient to satisfy the demand, there is no necessary to place an order.
  • Projected on hand inventory for week 7 is 120 units. Calculation is as follows:

Projected on hand for Week 7={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(300+0180)+0=120

Develop a material requirement planning for body:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  12

  • Base is the parent for body. Hence, the planned order release of the base would be the gross requirement of the body. As number of units required is 1 for body, the planned order release row of base should be multiplied with 1 to attain the gross requirement column of body.
  • Beginning inventory is 50 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 130 units in week 6 (180-50).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 3 weeks. Company requires 130 units in the beginning of Week 6. Hence, they need to order for 130 units (as the lot size is lot-for-lot) before three weeks (as the lead-time is 3 weeks). Thus, company need to order the required units in week 3.
  • Projected on hand inventory for week 7 is 0 units. Calculation is as follows:

Projected on hand for Week 7={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(50+130180)+0=0

Develop a material requirement planning for seats (2):

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  13

  • Base is the parent for seats. Hence, the planned order release of the base would be the gross requirement of the seats. As number of units required is 1 for seats, the planned order release row of base should be multiplied with 1 to attain the gross requirement column of seats.
  • Beginning inventory is 120 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 240 units in week 6 (360-120).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 2 weeks. Company requires 240 units in the beginning of Week 6. Hence, they need to order for 240 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks). Thus, company need to order the required units in week 4.
  • Projected on hand inventory for week 7 is 0 units. Calculation is as follows:

Projected on hand for Week 7={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(120+240360)+0=0

Develop a material requirement planning for frame:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  14

  • Body is the parent for frame. Hence, the planned order release of the body would be the gross requirement of the frame. As number of units required is 1 for frame, the planned order release row of body should be multiplied with 1 to attain the gross requirement column of frame.
  • Beginning inventory is 35 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 95 units in week 3 (130-35).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 95 units in the beginning of Week 3. Hence, they need to order for 95 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 2.
  • Projected on hand inventory for week 4 is 0 units. Calculation is as follows:

Projected on hand for Week 4={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(35+95130)+0=0

Develop a material requirement planning for controls:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  15

  • Body is the parent for controls. Hence, the planned order release of the body would be the gross requirement of the controls. As number of units required is 1 for controls, the planned order release row of body should be multiplied with 1 to attain the gross requirement column of controls.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 130 units in week 3 (130-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 130 units in the beginning of Week 3. Hence, they need to order for 130 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 2.

Develop a material requirement planning for wheel assemblies (4):

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 12, Problem 12P , additional homework tip  16

  • Body is the parent for wheel assemblies. Hence, the planned order release of the body would be the gross requirement of the wheel assemblies. As number of units required is 4 for wheel assemblies, the planned order release row of body should be multiplied with 4 to attain the gross requirement column of wheel assemblies.
  • Beginning inventory is 240 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 280 units in week 3 (520-240).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 280 units in the beginning of Week 3. Hence, they need to order for 280 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 2.
  • Projected on hand inventory for week 4 is 0 units. Calculation is as follows:

Projected on hand for Week 4={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(240+280520)+0=0

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas
I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to   use my forecast numbers to generate a Master Production Schedule (MPS)  I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022  April 2023  I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.

Chapter 12 Solutions

OPERATIONS MANAGEMENT(LL)-W/CONNECT

Ch. 12 - Prob. 7DRQCh. 12 - Briefly discuss the requirements for effective...Ch. 12 - Prob. 9DRQCh. 12 - How can the use of MRP contribute to productivity?Ch. 12 - Prob. 11DRQCh. 12 - What is lot sizing. what is its goal, and why is...Ch. 12 - Contrast planned-order receipts and scheduled...Ch. 12 - If seasonal variations are present, is their...Ch. 12 - Prob. 15DRQCh. 12 - What are some unforeseen costs of ERP?Ch. 12 - What trade-offs are involved in the decision to...Ch. 12 - Who in the organization needs to be involved in...Ch. 12 - Prob. 3TSCh. 12 - Prob. 1CTECh. 12 - Give one example of unethical behavior involving...Ch. 12 - a. Given the following diagram for a product,...Ch. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Eighty units of end item E are needed at the...Ch. 12 - a. One hundred twenty units of end item Z are...Ch. 12 - A table is assembled using three components, as...Ch. 12 - Eighty units of end item X are needed at the...Ch. 12 - Oh No!, Inc., sells three models of radar detector...Ch. 12 - Assume that you are the manager of a shop that...Ch. 12 - Assume that you are the manager of Assembly, Inc....Ch. 12 - Determine material requirements plans for pans N...Ch. 12 - A firm that produces electric golf carts has just...Ch. 12 - Refer to Problem 12. Assume that unusually mild...Ch. 12 - Using the accompanying diagram, do the following:...Ch. 12 - A company that manufactures paving material for...Ch. 12 - Prob. 16PCh. 12 - The MRP Department has a problem. Its computer...Ch. 12 - Develop a material requirements plan for component...Ch. 12 - How many wheels sets should the manager order?Ch. 12 - When should the wheel sets be ordered?Ch. 12 - Prob. 2.1CQCh. 12 - Prob. 1OTQCh. 12 - Prob. 2OTQCh. 12 - Suppose the company has just received an order for...Ch. 12 - Prob. 4OTQCh. 12 - Prob. 5OTQ
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY