Concept explainers
Using the accompanying diagram, do the following:
a. Draw a tree diagram for the scissors.
b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note: There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.
Use lot-for-lot ordering for all items.
a)
To prepare: Tree diagram for the scissors.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.
In addition to that, following diagram is given:
Prepare tree diagram for the scissors using given diagram:
b)
To prepare: A Material requirement planning for scissors.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.
In addition to that, following diagram is given:
Develop material requirement planning for scissors:
- It is given that 600 pairs of scissors are needed on day 6.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 6 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 6. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
Develop material requirement planning for bottom blade assembly:
- Scissor is the parent for bottom blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the bottom blade assembly. As number of units required is 1 for bottom blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of bottom blade assembly.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5(600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop material requirement planning for top blade assembly:
- Scissor is the parent for top blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the top blade assembly. As number of units required is 1 for top blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of top blade assembly.
- Beginning inventory is 40 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 5 (600-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 5. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
- Projected on hand inventory for week 6 is 0 units. Calculation is as follows:
Develop material requirement planning for screw:
- Scissor is the parent for screw. Hence, the planned order release of the scissor would be the gross requirement of the screw. As number of units required is 1 for screw, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of screw.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop material requirement planning for straight blade:
- Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
- Beginning inventory is 200 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 400 units in week 4(600-200).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 400 units in the beginning of Week 4. Hence, they need to order for 400 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop material requirement planning for straight plastic grip:
- Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 4 (600-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. Company requires 600 units in the beginning of Week 4. Hence, they need to order for 600 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
Develop material requirement planning for bent blade:
- Top blade assembly is the parent for bent blade. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent blade. As number of units required is 1 for bent blade, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent blade.
- Beginning inventory is 350 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 210 units in week 4 (560-350).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 210 units in the beginning of Week 4. Hence, they need to order for 210 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop material requirement planning for bent plastic grip:
- Top blade assembly is the parent for bent plastic grip. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent plastic grip. As number of units required is 1 for bent plastic grip, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent plastic grip.
- Beginning inventory is 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 4 (560-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 4. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3
Want to see more full solutions like this?
Chapter 12 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Principles Of Taxation For Business And Investment Planning 2020 Edition
FUNDAMENTALS OF CORPORATE FINANCE
Financial Accounting, Student Value Edition (5th Edition)
- pls some assistance :((arrow_forwardProduct M is made of two units of N and two of P. N is made of two units of R and four units of S. Ris made of one unit of S and three units of T. P is made of two units of T and four units of U. a. Show the bill-of-materials (product structure tree). b. If 100 Ms are required, how many units of each component are needed? c. Show both a single-level parts list and an indented parts list.arrow_forwardstep by step how does one complete an MRP matrix for item xarrow_forward
- 14. Using the accompanying diagram, do the following: a. Draw a tree diagram for the scissors. b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note: There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand. Use lot-for-lot ordering for all items. Bent plastic grip Top Straight blade Bottom 0 Straight plastic grip Bent blade Narrow_forwardRequirement Classify each of the cost items (a-h) into one of the business functions of the value chain. Cost Item Value Chain Business Function a. Utility costs for the plant assembling the Latitude computer line of products b. Distribution costs for shipping the Latitude line of products to a retail chain c. Payment to David Newbury Designs for design of the XPS 2-in-1 laptop d. Salary of computer scientist working on the next generation of servers e. Cost of Dell employees' visit to a major customer to demonstrate Dell's ability to interconnect with other computers f. Purchase of competitors' products for testing against potential Dell products g. Payment to business magazine for running Dell advertisements h. Cost of cartridges purchased from outside supplier to be used with Dell…arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forward
- Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 4,500 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 8,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 3,500 Week 1 2 3 Gross requirements 4,500 1,000…arrow_forwardShown below is a partially completed MPS record for ball bearings. Part 2 a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity on Hand: 400 Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 350 350 450 250 300 250 350 400 350 Customer orders (booked) 300 350 250 300 150 150 150 150 100 50 Projected on-hand inventory enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here MPS quantity 500 enter your response here enter your response here enter your response here enter your…arrow_forward
- As the production planner for Xiangling HuProducts, Inc., you have been given a bill of material fora bracket that is made up of a base, two springs, and fourclamps. The base is assembled from one clamp and twohousings. Each clamp has one handle and one casting. Eachhousing has two bearings and one shaft. There is no inventoryon hand. a) Design a product structure noting the quantities for eachitem and show the low-level coding.b) Determine the gross quantities needed of each item if youare to assemble 50 brackets.c) Compute the net quantities needed if there are 25 of thebase and 100 of the clamp in stock.arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forwardThe following table lists the components needed to assemble an end item. Assume there is no on-hand inventories. Item Direct Components End item A(4), B(5), C(4) A E(3), F(2) B D(3), E(5) C F(4) D E F E(4) If 3 units of the end item are to be assembled, how many units of component E are needed? Input should be an exact number.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.