OPERATIONS MANAGEMENT W/ CNCT+
OPERATIONS MANAGEMENT W/ CNCT+
12th Edition
ISBN: 9781259574931
Author: Stevenson
Publisher: MCG CUSTOM
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 12, Problem 14P

Using the accompanying diagram, do the following:

a. Draw a tree diagram for the scissors.

b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note: There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.

Use lot-for-lot ordering for all items.

Chapter 12, Problem 14P, Using the accompanying diagram, do the following: a. Draw a tree diagram for the scissors. b.

a)

Expert Solution
Check Mark
Summary Introduction

To prepare: Tree diagram for the scissors.

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).

Explanation of Solution

Given information:

Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.

In addition to that, following diagram is given:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  1

Prepare tree diagram for the scissors using given diagram:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  2

b)

Expert Solution
Check Mark
Summary Introduction

To prepare: A Material requirement planning for scissors.

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).

Explanation of Solution

Given information:

Lead-time is one day for all the components except plastic grips, which has the lead-time of 2 days. 600 pairs of scissors are needed on day 6. There are 350 bent blades, 200 straight blades, and 40 top blade assemblies on hand. Lot size is lot-for-lot ordering for all items.

In addition to that, following diagram is given:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  3

Develop material requirement planning for scissors:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  4

  • It is given that 600 pairs of scissors are needed on day 6.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 6 (600-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 6. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.

Develop material requirement planning for bottom blade assembly:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  5

  • Scissor is the parent for bottom blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the bottom blade assembly. As number of units required is 1 for bottom blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of bottom blade assembly.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5(600-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.

Develop material requirement planning for top blade assembly:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  6

  • Scissor is the parent for top blade assembly. Hence, the planned order release of the scissor would be the gross requirement of the top blade assembly. As number of units required is 1 for top blade assembly, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of top blade assembly.
  • Beginning inventory is 40 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 5 (600-40).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 5. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
  • Projected on hand inventory for week 6 is 0 units. Calculation is as follows:

Projected on hand for Week 6={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(40+560600)+0=0

Develop material requirement planning for screw:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  7

  • Scissor is the parent for screw. Hence, the planned order release of the scissor would be the gross requirement of the screw. As number of units required is 1 for screw, the planned order release row of scissor should be multiplied with 1 to attain the gross requirement column of screw.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 5 (600-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 600 units in the beginning of Week 5. Hence, they need to order for 600 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.

Develop material requirement planning for straight blade:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  8

  • Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
  • Beginning inventory is 200 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 400 units in week 4(600-200).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 400 units in the beginning of Week 4. Hence, they need to order for 400 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
  • Projected on hand inventory for week 5 is 0 units. Calculation is as follows:

Projected on hand for Week 5={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(200+400600)+0=0

Develop material requirement planning for straight plastic grip:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  9

  • Bottom blade assembly is the parent for straight blade. Hence, the planned order release of the bottom blade assembly would be the gross requirement of the straight blade. As number of units required is 1 for straight blade, the planned order release row of bottom blade assembly should be multiplied with 1 to attain the gross requirement column of straight blade.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 600 units in week 4 (600-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 2 weeks. Company requires 600 units in the beginning of Week 4. Hence, they need to order for 600 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.

Develop material requirement planning for bent blade:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  10

  • Top blade assembly is the parent for bent blade. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent blade. As number of units required is 1 for bent blade, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent blade.
  • Beginning inventory is 350 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 210 units in week 4 (560-350).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 210 units in the beginning of Week 4. Hence, they need to order for 210 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
  • Projected on hand inventory for week 5 is 0 units. Calculation is as follows:

Projected on hand for Week 5={(Projected on-hand+Planned order receiptGross requirement)+Scheduled receipt}=(350+210560)+0=0

Develop material requirement planning for bent plastic grip:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 12, Problem 14P , additional homework tip  11

  • Top blade assembly is the parent for bent plastic grip. Hence, the planned order release of the top blade assembly would be the gross requirement of the bent plastic grip. As number of units required is 1 for bent plastic grip, the planned order release row of top blade assembly should be multiplied with 1 to attain the gross requirement column of bent plastic grip.
  • Beginning inventory is 0 units.
  • Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 560 units in week 4 (560-0).
  • Planned order release is the order given by the company and planned order receipts is the order received by the firm.
  • Lead-time is given as 1 week. Company requires 560 units in the beginning of Week 4. Hence, they need to order for 560 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Draw a simple bill-of-materials (BOM) for a smart phone given the following requirements: (a) clearly label the end item and each component, (b) the BOM must contain no more than ten items, (c) the BOM must contain at least three levels (you may count the end-item level zero).
Using the accompanying diagram, do the following:a. Draw a tree diagram for the scissors.b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissorassembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note:There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.Use lot-for-lot ordering for all items.
Table B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B).   Table A   Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7   Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B   Item: Ball bearings   Quantity on hand: 400 Order policy: 500 units Lead time: 1 week   Week   1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory                     MPS quantity 500                   MPS start                     Available to promise (ATP)

Chapter 12 Solutions

OPERATIONS MANAGEMENT W/ CNCT+

Ch. 12 - Prob. 7DRQCh. 12 - Briefly discuss the requirements for effective...Ch. 12 - Prob. 9DRQCh. 12 - How can the use of MRP contribute to productivity?Ch. 12 - Prob. 11DRQCh. 12 - What is lot sizing. what is its goal, and why is...Ch. 12 - Contrast planned-order receipts and scheduled...Ch. 12 - If seasonal variations are present, is their...Ch. 12 - Prob. 15DRQCh. 12 - What are some unforeseen costs of ERP?Ch. 12 - What trade-offs are involved in the decision to...Ch. 12 - Who in the organization needs to be involved in...Ch. 12 - Prob. 3TSCh. 12 - Prob. 1CTECh. 12 - Give one example of unethical behavior involving...Ch. 12 - a. Given the following diagram for a product,...Ch. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Eighty units of end item E are needed at the...Ch. 12 - a. One hundred twenty units of end item Z are...Ch. 12 - A table is assembled using three components, as...Ch. 12 - Eighty units of end item X are needed at the...Ch. 12 - Oh No!, Inc., sells three models of radar detector...Ch. 12 - Assume that you are the manager of a shop that...Ch. 12 - Assume that you are the manager of Assembly, Inc....Ch. 12 - Determine material requirements plans for pans N...Ch. 12 - A firm that produces electric golf carts has just...Ch. 12 - Refer to Problem 12. Assume that unusually mild...Ch. 12 - Using the accompanying diagram, do the following:...Ch. 12 - A company that manufactures paving material for...Ch. 12 - Prob. 16PCh. 12 - The MRP Department has a problem. Its computer...Ch. 12 - Develop a material requirements plan for component...Ch. 12 - How many wheels sets should the manager order?Ch. 12 - When should the wheel sets be ordered?Ch. 12 - Prob. 2.1CQCh. 12 - Prob. 1OTQCh. 12 - Prob. 2OTQCh. 12 - Suppose the company has just received an order for...Ch. 12 - Prob. 4OTQCh. 12 - Prob. 5OTQ

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY