
Concept explainers
Nowjuice, Inc., produces Shakewell® fruit juice. A planner has developed an aggregate
Use the following information to develop aggregate plans.
Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan. Which plan has the lowest total cost? Note: Backlogs are not allowed.
a. Use level production. Supplement using overtime as needed.
b. Use a combination of overtime (500 cases per period maximum), inventory, and subcontracting (500 cases per period maximum) to handle variations in demand.
C. Use overtime up to 750 cases per period and inventory to handle variations in demand.
a)

To determine: The total cost using level strategy of aggregate planning.
Introduction: Level production strategy is a production strategy used to produce at a constant rate. This strategy keeps constant level of workforce and backlog of demand.
Answer to Problem 8P
Explanation of Solution
Given information:
Regular production cost is $10, overtime production cost is $16, subcontracting cost is $20, holding cost is $1, regular capacity is 5,000 units, and beginning inventory is given as 0 units. In addition to this forecast for 6 months is given as follows:
Month | July | June | July | August | September | October | Total |
Forecast | 4,000 | 4,800 | 5,600 | 7,200 | 6,400 | 5,000 | 33,000 |
Determine the total cost of the plan:
It is given that regular productions should be used. No backlogs are allowed. Supplements can be satisfied using overtime.
Supporting explanation:
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 1,000 units.
Calculate the difference for the month of June:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 1,000 units.
Calculate the difference for the month of July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -600 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 1,000 units.
Ending inventory for the month of June:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 1,200 units.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 600 units.
Note: The calculation repeats for all the months.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 500 units.
Average inventory for the month of June:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1,100 units.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 900 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Calculate the regular time cost for the month of June:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $300,000.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $16 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of June:
Overtime cost per unit is given as $16 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $16 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of August:
Overtime cost per unit is given as $16 and overtime unit is given as 1,600. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $25,600.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 48,000.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of June:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $0.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $500.
Calculate the inventory cost for the month of June:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $1,100.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $900.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $2,800.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $350,800.
b)

To determine: The total cost using level strategy of aggregate planning.
Introduction: Level production strategy is a production strategy used to produce at a constant rate. This strategy keeps constant level of workforce and backlog of demand.
Answer to Problem 8P
Explanation of Solution
Given information:
Regular production cost is $10, overtime production cost is $16, subcontracting cost is $20, holding cost is $1, regular capacity is 5,000 units, and beginning inventory is given as 0 units. Maximum subcontract capacity is 500 units and maximum overtime capacity is 500 units. In addition to this forecast for 6 months is given as follows:
Month | July | June | July | August | September | October | Total |
Forecast | 4,000 | 4,800 | 5,600 | 7,200 | 6,400 | 5,000 | 33,000 |
Determine the total cost of the plan:
It is given that regular productions should be used. No backlogs are allowed. Supplements can be satisfied using overtime.
Supporting explanation:
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 1,500 units.
Calculate the difference for the month of June:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 700 units.
Calculate the difference for the month of July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -100 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 1,500 units.
Ending inventory for the month of June:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 2,200 units.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 2,100 units.
Note: The calculation repeats for all the months.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 750 units.
Average inventory for the month of June:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1,850 units.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2,150 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Calculate the regular time cost for the month of June:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $300,000.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $16 and overtime unit is given as 500. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $8,000.
Calculate the overtime cost for the month of June:
Overtime cost per unit is given as $16 and overtime unit is given as 500. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $8,000.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $16 and overtime unit is given as 500. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $8,000.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 40,000.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of June:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $10,000.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $750.
Calculate the inventory cost for the month of June:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $1,850.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $2,150.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $6,200.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $356,200.
c)

To determine: The total cost using aggregate planning.
Introduction: Level production strategy is a production strategy used to produce at a constant rate. This strategy keeps constant level of workforce and backlog of demand.
Answer to Problem 8P
Explanation of Solution
Given information:
Regular production cost is $10, overtime production cost is $16, subcontracting cost is $20, holding cost is $1, regular capacity is 5,000 units, overtime capacity is 750 units, and beginning inventory is given as 0 units. In addition to this forecast for 6 months is given as follows:
Month | July | June | July | August | September | October | Total |
Forecast | 4,000 | 4,800 | 5,600 | 7,200 | 6,400 | 5,000 | 33,000 |
Determine the total cost of the plan:
It is given that regular productions should be used. No backlogs are allowed. Supplements can be satisfied using overtime.
Supporting explanation:
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 1,000 units.
Calculate the difference for the month of June:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 950 units.
Calculate the difference for the month of July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 150 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 1,000 units.
Ending inventory for the month of June:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 1,950 units.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 2,100 units.
Note: The calculation repeats for all the months.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 500 units.
Average inventory for the month of June:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1,475 units.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2,025 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Calculate the regular time cost for the month of June:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $10 and regular time unit is given as 5,000. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $50,000.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $300,000.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $16 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of June:
Overtime cost per unit is given as $16 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $16 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of August:
Overtime cost per unit is given as $16 and overtime unit is given as 1,600. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $25,600.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 48,000.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $20 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of June:
Subcontract cost per unit is given as $20 and subcontract unit is given as 750. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $12,000.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $20 and subcontract unit is given as 750. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $12,000.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $48,000.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $500.
Calculate the inventory cost for the month of June:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $1,475.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $2,025.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $5,700.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $350,800.
Conclusion: Plan from Part (a) should be selected, as it has the lowest cost ($350,800).
Want to see more full solutions like this?
Chapter 11 Solutions
EBK OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Foundations of Financial Management
Essentials of Corporate Finance (Mcgraw-hill/Irwin Series in Finance, Insurance, and Real Estate)
Essentials of MIS (13th Edition)
- Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 2 36 28 4 1 Use a production lot size of 85 units and no beginning inventory. Note: In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required. June July 1 2 3 4 5 8 7 8 Forecast 60 60 60 60 60 60 60 60 Customer Orders 38 28 4 1 0 0 0 0 Projected On-Hand Inventory MPS ATParrow_forwardSales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 Forecast 21.0 21 21 24 31 28 29 32 28 26.50 b) For the forecast developed using exponential smoothing (a = 0.50 and initial forecast 21.0), the MAD = |||||sales (round your response to two decimal places).arrow_forwardSales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week Demand 1 2 3 4 5 6 7 8 9 10 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 Demand 21 21 27 38 Forecast 21.0 ☐ G ☐ ☐ 6 7 25 30 35 ∞ ☐ 8 9 10 24 25 30arrow_forward
- Each machine costs $3 Million. Building the room with all its attendant safety protection and other ancillary costs increases the spending by an additional $2.0 million dollars per MRI suite. Each machine can perform 2000 scans per year. Each reading of an MRI scan by a radiologist, along with other per-scan-related costs, is $500 per scan. The machine will last five years. Don’t worry about discount rates for this problem Graph the total costs over 5 years as a function of sales for 0-3000 patients annually. Hint: you may need to add a second MRI at some point. Suppose that you want to make a profit of $500 per scan at a target volume of 1000 patients per year, and you purchase only one machine. Superimpose the total revenue curve on top of the total cost curve in (1).arrow_forwardI need the answer to requirement C.arrow_forwardImagine you are Susan Kim and are faced with a difficult choice to either follow the orders she was given, or refusing to do so. Using each lens determine what the ethical response would be. Suppot your answer with materials from readings and lectures. For example, using Universalism what would the ethical response be? Do the same for all four lenses.arrow_forward
- Answer all these questions, selecting any company of your choice. Choose a specific type of food company. Select a specific product. Develop all the inputs that are part of the process. Develop the transformation process in a graphic (diagram, etc.). Develop all the outputs or finished products that are part of the process. Describe all the processes involved in one line of production in any manufacturing facility. Also describing how good management is the center of any part of a production company.arrow_forwardUsing exponential smoothing with α =0.2, forecast the demand for The initial forecast for January is 2000 tons. Calculate the capacity utilization for June, July and Discuss the implications of underutilized or over utilized capacity for Green Harvestarrow_forwardIn organizational development when results are improving but relationships are declining, what leadership style is appropriate? directing delegating supporting coachingarrow_forward
- What is the first thing a leader should do when moving through a cultural change? conduct an assessment comparing the practices to other high-performing organizations learn about the current organizational culture continue to monitor key metrics define expectationsarrow_forwardThe third change leadership strategy, Collaborate on Implementation, is designed to address what type of concerns? impact concerns personal concerns refinement concerns collaboration concernsarrow_forwardIf team members are concerned with specifics such as their tasks, contingency plans, resources, and timeline, what concerns do they have? implementation concerns impact concerns refinement concerns personal concernsarrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning


