Question
Book Icon
Chapter 11, Problem 19P

1)

To determine

Delivery Cycle, Throughput Time, Manufacturing Cycle Efficiency:

The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

It consists of throughput time, Value added time and non-value added time.

To depict delivery cycle in the formula form, the following formula maybe used:

Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

  • Throughput Time
  • Delivery Cycle
  • Manufacturing Cycle Efficiency

1)

Expert Solution
Check Mark

Answer to Problem 19P

Solution:

    Average Time per month (in days)
    Particulars 1 2 3 4
    Throughput Time 7.30 8.10 8.80 9.60
    Delivery Cycle 16.30 19.60 20.80 23.60
    Manufacturing Cycle Efficiency 0.29 0.25 0.22 0.19

Explanation of Solution

  • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
  • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
  • Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products
  • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
  • Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent
  • Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.
  • Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.
  • Given:
    Average Time per month (in days)
    Particulars 1.0 2.0 3.0 4.0
    Move time per unit 0.3 0.4 0.4 0.5
    Process Time per unit 2.1 2.0 1.9 1.8
    Wait time per order 9.0 11.5 12.0 14.0
    Queue Time per unit 4.3 5.0 5.8 6.7
    Inspection Time per unit 0.6 0.7 0.7 0.6
  • Formulas Used:
  • Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)
  • Delivery Cycle = Non Value Added activities + Total Throughput Time
  • Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
  • Time Taken by value added activities = Time taken for Process Time
  • Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time
  • Calculations:
    Average Time per month (in days)
    Particulars 1.0 2.0 3.0 4.0
    Move time per unit 0.3 0.4 0.4 0.5
    Queue Time per unit 4.3 5.0 5.8 6.7
    Inspection Time per unit 0.6 0.7 0.7 0.6
    Total Time For Non Value Added Activities (A) 5.2 6.1 6.9 7.8
    Process Time per unit 2.1 2.0 1.9 1.8
    Total Time For Non Value Added Activities (B) 2.1 2.0 1.9 1.8
    Throughput Time (A+B) [C] 7.3 8.1 8.8 9.6
    Wait time per order [D] 9.0 11.5 12.0 14.0
    Delivery Cycle (C+D) 16.3 19.6 20.8 23.6
    Manufacturing Cycle Efficiency Time Taken by value added activities / Total Throughput Time.
    Manufacturing Cycle Efficiency 0.29 0.25 0.22 0.19
Conclusion

Hence the throughput time, delivery cycle, and manufacturing cycle efficiency has been calculated for each months.

2)

Evaluation of Manufacturing Cycle efficiency and its’ components

The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

It consists of throughput time, Value added time and non-value added time.

To depict delivery cycle in the formula form, the following formula maybe used:

Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

Hence evaluation has to be done of the following parameters:

  1. Throughput time
  2. Delivery Cycle Time
  3. Manufacturing Cycle Efficiency
To determine

  • Areas where company’s performance is improving.
  • Areas where company’s performance is deteriorating.

Expert Solution
Check Mark

Answer to Problem 19P

Solution:

  • Areas where company’s performance is improving are None
  • Areas where company’s performance is deteriorating are throughput time and delivery cycle time and manufacturing cycle efficiency.

Explanation of Solution

  • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
  • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
  • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
  • Following are the Throughput time for four months:
    Average Time per month (in days)
    Particulars 1 2 3 4
    Throughput Time 7.30 8.10 8.80 9.60
  • Since the total throughput time is increasing, it can be said the company’s performance is deteriorating.
  • The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.
  • Following are the Delivery cycle times for four months:
    Average Time per month (in days)
    Particulars 1 2 3 4
    Delivery Cycle 16.30 19.60 20.80 23.60
  • Since the total delivery cycle time is increasing, it can be said the company’s performance is deteriorating.
  • Manufacturing cycle efficiency helps keep track of where time and cost is incurred in non-value added activities and performance efficiency measurement.
  • Manufacturing cycle efficiency is denoted by the following formula:

    Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.

Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities

  • For example if the time Taken by value added activities is 25 minutes per unit and the Time Taken by non-value added activities is 35 minutes then manufacturing cycle efficiency would be 0.42.
  • Thus it can be interpreted as, the value added activities take up only 42 % of the total time taken to complete the manufacturing process and the rest is attributable to non-value added activities.
  • Following are the Manufacturing cycle efficiency for four months:
    • Average Time per month (in days)
      Particulars 1 2 3 4
      Manufacturing Cycle Efficiency 0.29 0.25 0.22 0.19
    • Since the Manufacturing Cycle Efficiency is decreasing, the company’s performance is deteriorating.
    Conclusion

    Hence the performance measures where the company’s performance is increasing and decreasing are enumerated.

    3)

    a)

    Throughput Time, Manufacturing Cycle Efficiency

    The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

    It consists of throughput time, Value added time and non-value added time.

    To depict delivery cycle in the formula form, the following formula maybe used:

    Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

    Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

    To determine

    • Throughput Time for Month 5
    • Manufacturing Cycle Efficiency for Month 5

    Expert Solution
    Check Mark

    Answer to Problem 19P

    Solution:

      Average Time per month (in days)
      Particulars 4 5
      Throughput Time 9.60 2.90
      Manufacturing Cycle Efficiency for month 5 0.19 0.62

    Explanation of Solution

    • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
    • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
    • Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products
    • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
    • Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent
    • Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.
    • Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.
    • Given:
      Particulars 4 5
      Move time per unit 0.5 0.5
      Queue Time per unit 6.7 0.0
      Inspection Time per unit 0.6 0.6
      Process Time per unit 1.8 1.8
  • Formulas Used:
    • Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)
    • Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
    • Time Taken by value added activities = Time taken for Process Time
    • Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time
    • Calculations:
      Average Time per month (in days)
      Particulars 4 5
      Move time per unit 0.5 0.5
      Queue Time per unit 6.7 0.0
      Inspection Time per unit 0.6 0.6
      Total Time For Non Value Added Activities (A) 7.8 1.1
      Process Time per unit 1.8 1.8
      Total Time For Value Added Activities (B) 1.8 1.8
      Throughput Time (A+B) [C] 9.6 2.9
      Manufacturing Cycle Efficiency Time Taken by value added activities / Total Throughput Time.
      Manufacturing Cycle Efficiency 0.19 0.62
  • Since it is given that the lean production has eliminated the queue time, the same is not considered.
  • Conclusion

    Hence the throughput time and manufacturing cycle efficiency has been calculated for month 5.

    3)

    b)

    Throughput Time, Manufacturing Cycle Efficiency

    The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.

    It consists of throughput time, Value added time and non-value added time.

    To depict delivery cycle in the formula form, the following formula maybe used:

    Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.

    Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.

    To determine

    • Throughput Time for Month 6
    • Manufacturing Cycle Efficiency for Month 6

    Expert Solution
    Check Mark

    Answer to Problem 19P

    Solution:

      Average Time per month (in days)
      Particulars 4 6
      Throughput Time 9.60 2.30
      Manufacturing Cycle Efficiency for month 6 0.19 0.78

    Explanation of Solution

    • Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
    • Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
    • Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products
    • Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
    • Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent
    • Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.
    • Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.
    • Given:
      Particulars 4 6
      Move time per unit 0.5 0.5
      Queue Time per unit 6.7 0.0
      Inspection Time per unit 0.6 0.0
      Process Time per unit 1.8 1.8
  • Formulas Used:
    • Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)
    • Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
    • Time Taken by value added activities = Time taken for Process Time
    • Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time
    • Calculations:
      Average Time per month (in days)
      Particulars 4 6
      Move time per unit 0.5 0.5
      Queue Time per unit 6.7 0.0
      Inspection Time per unit 0.6 0.0
      Total Time For Non Value Added Activities (A) 7.8 0.5
      Process Time per unit 1.8 1.8
      Total Time For Value Added Activities (B) 1.8 1.8
      Throughput Time (A+B) [C] 9.6 2.3
      Manufacturing Cycle Efficiency Time Taken by value added activities / Total Throughput Time.
      Manufacturing Cycle Efficiency 0.19 0.78
  • Since it is given that the lean production has eliminated the queue time and inspection time, the same is not considered.
  • Conclusion

    Hence the throughput time and manufacturing cycle efficiency has been calculated for month 6.

    Want to see more full solutions like this?

    Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
    Students have asked these similar questions
    Problem 3-2B Preparing adjusting and subsequent journal entries P1 P2 P3 P4 Natsu Company's annual accounting period ends on October 31. The following information concerns the adjusting entries that need to be recorded as of that date. Entries can draw from the following partial chart of accounts: Cash; Accounts Receivable; Office Supplies; Prepaid Insurance; Building; Accumulated Depreciation- Building; Salaries Payable; Unearned Revenue; Rent Revenue; Salaries Expense; Office Supplies Expense; Insurance Expense; and Depreciation Expense-Building. a. b. c. d. e. f. The Office Supplies account started the fiscal year with a $600 balance. During the fiscal year, the company purchased supplies for $4,570, which was added to the Office Supplies account. The supplies available at October 31 totaled $800. The Prepaid Insurance account had a $12,000 debit balance at October 31 before adjusting for the costs of any expired coverage for the fiscal year. An analysis of prepaid insurance shows…
    Problem 3-1B Identifying adjusting entries with explanations P1 P2 P3 P4 For journal entries 1 through 12, indicate the explanation that most closely describes it. You can use explanations more than once. A. To record payment of a prepaid expense. B. To record this period's use of a prepaid expense. C. To record this period's depreciation expense. D. To record receipt of unearned revenue. E. To record this period's earning of prior unearned revenue. F. To record an accrued expense. G. To record payment of an accrued expense. H. To record an accrued revenue. I. To record receipt of accrued revenue. 1. Interest Receivable 3,500 7. Cash 1,500 Interest Revenue 3,500 Accounts Receivable (from services) 1,500 2. Salaries Payable 9,000 8. Salaries Expense 7,000 Cash 9,000 Salaries Payable 7,000 3. Depreciation Expense 8,000 9. Cash 1,000 Accumulated Depreciation. 8,000 Interest Receivable 1,000 4. Cash 9,000 10. Unearned Revenue 9,000 Prepaid Rent Cash 3,000 3,000 5. Insurance Expense 4,000…
    None

    Chapter 11 Solutions

    Managerial Accounting

    Knowledge Booster
    Background pattern image
    Accounting
    Learn more about
    Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
    Similar questions
    SEE MORE QUESTIONS
    Recommended textbooks for you
    Text book image
    FINANCIAL ACCOUNTING
    Accounting
    ISBN:9781259964947
    Author:Libby
    Publisher:MCG
    Text book image
    Accounting
    Accounting
    ISBN:9781337272094
    Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
    Publisher:Cengage Learning,
    Text book image
    Accounting Information Systems
    Accounting
    ISBN:9781337619202
    Author:Hall, James A.
    Publisher:Cengage Learning,
    Text book image
    Horngren's Cost Accounting: A Managerial Emphasis...
    Accounting
    ISBN:9780134475585
    Author:Srikant M. Datar, Madhav V. Rajan
    Publisher:PEARSON
    Text book image
    Intermediate Accounting
    Accounting
    ISBN:9781259722660
    Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
    Publisher:McGraw-Hill Education
    Text book image
    Financial and Managerial Accounting
    Accounting
    ISBN:9781259726705
    Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
    Publisher:McGraw-Hill Education
    Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license