1)
Delivery Cycle, Throughput Time, Manufacturing Cycle Efficiency
The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.
It consists of throughput time, Value added time and non-value added time.
To depict delivery cycle in the formula form, the following formula maybe used:
Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.
Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.
To Determine:
- Throughput Time
- Delivery Cycle
- Manufacturing Cycle Efficiency
1)

Answer to Problem 14P
Solution:
| Average Time per month (in days) | |||
Particulars | 1 | 2 | 3 | 4 |
Throughput Time | 7.40 | 8.00 | 8.80 | 9.50 |
Delivery Cycle | 23.40 | 25.50 | 27.80 | 30.00 |
Manufacturing Cycle Efficiency | 0.23 | 0.24 | 0.25 | 0.26 |
Explanation of Solution
- Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
- Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
- Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products
- Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
- Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent
- Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.
- Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.
- Given:
| Average Time per month (in days) | |||
Particulars | 1.0 | 2.0 | 3.0 | 4.0 |
Move time per unit | 0.4 | 0.3 | 0.4 | 0.4 |
Process Time per unit | 2.1 | 2.0 | 1.9 | 1.8 |
Wait time per order | 16.0 | 17.5 | 19.0 | 20.5 |
Queue Time per unit | 4.3 | 5.0 | 5.8 | 6.7 |
Inspection Time per unit | 0.6 | 0.7 | 0.7 | 0.6 |
- Formulas Used:
- Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)
- Delivery Cycle = Non Value Added activities + Total Throughput Time
- Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
- Time Taken by value added activities = Time taken for Process Time
- Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time
- Calculations:
| Average Time per month (in days) | |||
Particulars | 1.0 | 2.0 | 3.0 | 4.0 |
Move time per unit | 0.4 | 0.3 | 0.4 | 0.4 |
Queue Time per unit | 4.3 | 5.0 | 5.8 | 6.7 |
Inspection Time per unit | 0.6 | 0.7 | 0.7 | 0.6 |
Total Time For Non Value Added Activities (A) | 5.3 | 6.0 | 6.9 | 7.7 |
Process Time per unit | 2.1 | 2.0 | 1.9 | 1.8 |
Total Time For Value Added Activities (B) | 2.1 | 2.0 | 1.9 | 1.8 |
Throughput Time (A+B) [C] | 7.4 | 8.0 | 8.8 | 9.5 |
Wait time per order [D] | 16.0 | 17.5 | 19.0 | 20.5 |
Delivery Cycle (C+D) | 23.4 | 25.5 | 27.8 | 30.0 |
Manufacturing Cycle Efficiency | Time Taken by value added activities / Total Throughput Time. | |||
Manufacturing Cycle Efficiency | 22.65% | 23.53% | 24.82% | 25.67% |
Hence the throughput time, delivery cycle, and manufacturing cycle efficiency has been calculated for each months.
2)
Delivery Cycle, Throughput Time, Manufacturing Cycle Efficiency
The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.
It consists of throughput time, Value added time and non-value added time.
To depict delivery cycle in the formula form, the following formula maybe used:
Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.
Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.
To Determine:
Evaluation of the company’s performance over the months
2)

Answer to Problem 14P
Solution:
The performance has improved over the last few months.
Explanation of Solution
- Manufacturing cycle efficiency helps keep track of where time and cost is incurred in non-value added activities and performance efficiency measurement.
- Manufacturing cycle efficiency is denoted by the following formula:
Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities
- For example if the time Taken by value added activities is 25 minutes per unit and the Time Taken by non-value added activities is 35 minutes then manufacturing cycle efficiency would be 0.42.
- Thus it can be interpreted as, the value added activities take up only 42 % of the total time taken to complete the manufacturing process and the rest is attributable to non-value added activities.
- Given:
| Average Time per month (in days) | |||
Particulars | 1 | 2 | 3 | 4 |
Manufacturing Cycle Efficiency | 0.23 | 0.24 | 0.25 | 0.26 |
- If manufacturing cycle efficiency is 0.23, then it means that non value added activities contribute to 77% of the total throughput time and production process.
- Since the manufacturing cycle efficiency is increasing with every month, it can be said that the time taken by non-value added activities is reducing.
Hence it can be said that the Manufacturing cycle efficiency improves, the time taken by non value added activities reduces.
3)
a)
Throughput Time, Manufacturing Cycle Efficiency
The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.
It consists of throughput time, Value added time and non-value added time.
To depict delivery cycle in the formula form, the following formula maybe used:
Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.
Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.
To Determine:
- Throughput Time for Month 5
- Manufacturing Cycle Efficiency for Month 5
3)
a)

Answer to Problem 14P
Solution:
| Average Time per month (in days) | |||
Particulars | 4 | 5 | ||
Throughput Time | 9.50 | 2.80 | ||
| | | ||
Manufacturing Cycle Efficiency for month 5 | 0.26 | 0.64 |
Explanation of Solution
- Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
- Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
- Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products
- Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
- Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent
- Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.
- Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.
Given:
| Average Time per month (in days) | |||
Particulars | 4 | 5 | 6 | |
Move time per unit | 0.4 | 0.4 | ||
Queue Time per unit | 6.7 | 0.0 | ||
Inspection Time per unit | 0.6 | 0.6 | ||
Process Time per unit | 1.8 | 1.8 |
Formulas Used:
- Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)
- Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
- Time Taken by value added activities = Time taken for Process Time
- Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time
Calculations:
| Average Time per month (in days) | |||
Particulars | 4 | 5 | ||
Move time per unit | 0.4 | 0.4 | ||
Queue Time per unit | 6.7 | 0.0 | ||
Inspection Time per unit | 0.6 | 0.6 | ||
Total Time For Non Value Added Activities (A) | 7.7 | 1.0 | ||
Process Time per unit | 1.8 | 1.8 | ||
Total Time For Value Added Activities (B) | 1.8 | 1.8 | ||
Throughput Time (A+B) [C] | 9.5 | 2.8 | ||
| | | ||
Manufacturing Cycle Efficiency | Time Taken by value added activities / Total Throughput Time. | |||
Manufacturing Cycle Efficiency | 0.26 | 0.64 |
- Since it is given that the lean production has eliminated the queue time, the same is not considered.
Hence the throughput time and manufacturing cycle efficiency has been calculated for month 5.
3)
b)
Throughput Time, Manufacturing Cycle Efficiency
The time taken from the start of the sale process, i.e. the receipt of a confirmed sales order, to the completion of the transfer of goods or services, i.e. dispatch of goods is known as the Delivery Cycle.
It consists of throughput time, Value added time and non-value added time.
To depict delivery cycle in the formula form, the following formula maybe used:
Delivery Cycle = Value added Elements of Throughput Time + Non Value Added Elements of Throughput Time.
Manufacturing Cycle Efficiency is an internal business performance parameter with respect to manufacturing processes and industries. It measures the total time taken by value added activities in relation to the throughput time.
To Determine:
- Throughput Time for Month 6
- Manufacturing Cycle Efficiency for Month 6
3)
b)

Answer to Problem 14P
Solution:
| Average Time per month (in days) | |||
Particulars | 4 | 6 | ||
Throughput Time | 9.50 | 2.20 | ||
| | | ||
Manufacturing Cycle Efficiency for month 6 | 0.26 | 0.82 |
Explanation of Solution
- Throughput time comprises of two main categories of elements i.e. Value added and Non Value added elements.
- Value added elements refer to the time taken for those activities that add quality and value to the overall production process concerning manufacture of goods. Example − Process Time.
- Process time is the time spent on actually producing the product. It refers to the time taken to convert the goods from raw materials to interim or final finished products
- Non Value added elements refer to the time taken for those activities that do not add quality and value to the overall production process concerning manufacture of goods and that need to be eliminated to the greatest extent possible. Example - Inspection Time, Move Time and Queue time
- Inspection time is the amount of time spent assuring that the product is defect free to the best possible extent
- Move time is the time required to transfer raw materials or interim or final finished products from one location to another, such as factory to job workers’ location.
- Queue time is the amount of time that is spent waiting for the actually production activities to commence since other products are being produced or worked upon.
Given:
| ||
Particulars | 4 | 6 |
Move time per unit | 0.4 | 0.4 |
Queue Time per unit | 6.7 | 0.0 |
Inspection Time per unit | 0.6 | 0.0 |
Process Time per unit | 1.8 | 1.8 |
Formulas Used:
- Total Throughput Time = Time Taken by value added activities + Time Taken by Non value added activities (Except Wait Time)
- Manufacturing cycle efficiency = Time Taken by value added activities / Total Throughput Time.
- Time Taken by value added activities = Time taken for Process Time
- Time Taken by Non value added activities = Time taken for Move Time + Queue Time + Inspection Time
Calculations:
| Average Time per month (in days) | |
Particulars | 4 | 6 |
Move time per unit | 0.4 | 0.4 |
Queue Time per unit | 6.7 | 0.0 |
Inspection Time per unit | 0.6 | 0.0 |
Total Time For Non Value Added Activities (A) | 7.7 | 0.4 |
Process Time per unit | 1.8 | 1.8 |
Total Time For Value Added Activities (B) | 1.8 | 1.8 |
Throughput Time (A+B) [C] | 9.5 | 2.2 |
| | |
Manufacturing Cycle Efficiency | Time Taken by value added activities / Total Throughput Time. | |
Manufacturing Cycle Efficiency | 0.26 | 0.82 |
- Since it is given that the lean production has eliminated the queue time and inspection time, the same is not considered.
Hence the throughput time and manufacturing cycle efficiency has been calculated for month 6.
Want to see more full solutions like this?
Chapter 11 Solutions
MANAGERIAL ACCOUNTING W/CONNECT
- Consolidation after Several Years On January 1, 2016, Adams Corporation acquired all of the stock of Baker Company. The fair value of Adams’ shares used in the exchange was $37,500,000. At the time of acquisition, the book value of Baker’s shareholders’ equity was $5,000,000, and the book value of Baker’s building (25-year life) exceeded its fair value by $1,000,000. From the date of acquisition to December 31, 2021, Baker had cumulative net income of $1,300,000. For 2022, Baker reported net income of $300,000. Adams uses the complete equity method to account for its investment in Baker. There is no goodwill impairment loss for the period 2016 through 2021, but there is impairment loss of $100,000 in 2022. Baker declared no dividends during the period 2016–2022. Required Prepare the working paper eliminating entries necessary to consolidate the financial statements of Adams and Baker at December 31, 2022. Enter numerical answers using all zeros (do not abbreviate in thousands or in…arrow_forwardGive me the answer in a clear organized table please. Thank you!arrow_forwardGive me the answer in a clear organized table please. Thank you!arrow_forward
- Assess the role of the Conceptual Framework in financial reporting and its influence on accounting theory and practice. Discuss how the qualitative characteristics outlined in the Conceptual Framework enhance financial reporting and contribute to decision-usefulness. Provide examplesarrow_forwardCurrent Attempt in Progress Cullumber Corporation has income from continuing operations of $464,000 for the year ended December 31, 2025. It also has the following items (before considering income taxes). 1. An unrealized loss of $128,000 on available-for-sale securities. 2. A gain of $48,000 on the discontinuance of a division (comprised of a $16,000 loss from operations and a $64,000 gain on disposal). Assume all items are subject to income taxes at a 20% tax rate. Prepare a partial income statement, beginning with income from continuing operations. Income from Continuing Operations Discontinued Operations Loss from Operations Gain from Disposal Net Income/(Loss) CULLUMBER CORPORATION Income Statement (Partial) For the Year Ended December 31, 2025 Prepare a statement of comprehensive income. Net Income/(Loss) $ CULLUMBER CORPORATION Statement of Comprehensive Income For the Year Ended December 31, 2025 = Other Comprehensive Income Unrealized Loss of Available-for-Sale Securities ✰…arrow_forwardPlease make a trial balance, adjusted trial balance, Income statement. end balance ,owners equity statement, Balance sheet , Cash flow statement ,Cash end balancearrow_forward
- Activity Based Costing - practice problem Fontillas Instrument, Inc. manufactures two products: missile range instruments and space pressure gauges. During April, 50 range instruments and 300 pressure gauges were produced, and overhead costs of $89,500 were estimated. An analysis of estimated overhead costs reveals the following activities. Activities 1. Materials handling 2. Machine setups Cost Drivers Number of requisitions Number of setups Total cost $35,000 27,500 3. Quality inspections Number of inspections 27,000 $89.500 The cost driver volume for each product was as follows: Cost Drivers Instruments Gauge Total Number of requisitions 400 600 1,000 Number of setups 200 300 500 Number of inspections 200 400 600 Insructions (a) Determine the overhead rate for each activity. (b) Assign the manufacturing overhead costs for April to the two products using activity-based costing.arrow_forwardBodhi Company has three cost pools and two doggie products (leashes and collars). The activity cost pool of ordering has the cost drive of purchase orders. The activity cost pool of assembly has a cost driver of parts. The activity cost pool of supervising has the cost driver of labor hours. The accumulated data relative to those cost drivers is as follows: Expected Use of Estimated Cost Drivers by Product Cost Drivers Overhead Leashes Collars Purchase orders $260,000 70,000 60,000 Parts 400,000 300,000 500,000 Labor hours 300,000 15,000 10,000 $960,000 Instructions: (a) Compute the activity-based overhead rates. (b) Compute the costs assigned to leashes and collars for each activity cost pool. (c) Compute the total costs assigned to each product.arrow_forwardTorre Corporation incurred the following transactions. 1. Purchased raw materials on account $46,300. 2. Raw Materials of $36,000 were requisitioned to the factory. An analysis of the materials requisition slips indicated that $6,800 was classified as indirect materials. 3. Factory labor costs incurred were $55,900, of which $51,000 pertained to factory wages payable and $4,900 pertained to employer payroll taxes payable. 4. Time tickets indicated that $50,000 was direct labor and $5,900 was indirect labor. 5. Overhead costs incurred on account were $80,500. 6. Manufacturing overhead was applied at the rate of 150% of direct labor cost. 7. Goods costing $88,000 were completed and transferred to finished goods. 8. Finished goods costing $75,000 to manufacture were sold on account for $103,000. Instructions Journalize the transactions.arrow_forward
- Chapter 15 Assignment of direct materials, direct labor and manufacturing overhead Stine Company uses a job order cost system. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 430 $2,500 3,500 $1,900 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at an overhead rate of 60% of direct labor cost. Instructions Prepare summary journal entries to record (i) the requisition slips, (ii) the time tickets, (iii) the assignment of manufacturing overhead to jobs,arrow_forwardSolve accarrow_forwardSolve fastarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education