Textbook Question
Chapter 11, Problem 11.36BE
Calculate missing direct material variables (Learning Objective 2)
Last month, Bugsby Corporation purchased and used the same quantity of material in producing its speed bumps, a traffic control product. Complete the following table:
Medium speed bump | Large speed bump | |
Standard pounds per unit | 15 | ? |
Standard price per pound | $ 3.50 | $3.90 |
Actual quantity purchased and used per unit | ? | 16 |
Actual price paid for material | $ 4.10 | $ 4.70 |
Direct materials price variance | $ 2,520 U | $ 7,680 U |
Direct materials quantity variance | $ 1,050 F | ? |
Total direct material variance | ? | $ 5,340 U |
Number of units produced | 300 | 600 |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
I don't need ai answer general accounting question
What specifies the accounting for multi-year insurance policies paid in advance? (a) Expense total premium immediately (b) Record as asset and amortize systematically (c) Recognize when coverage provided (d) Split between years equally
General accounting
Chapter 11 Solutions
EBK MANAGERIAL ACCOUNTING
Ch. 11 - (Learning Objective 1) Which of the following is...Ch. 11 - (Learning Objective 2) The direct material price...Ch. 11 - Prob. 3QCCh. 11 - Prob. 4QCCh. 11 - Prob. 5QCCh. 11 - (Learning Objective 4) Which of the following is...Ch. 11 - Prob. 7QCCh. 11 - (Learning Objective 6) Which of the following is...Ch. 11 - Prob. 9QCCh. 11 - (Learning Objective 7Appendix) Which of the...
Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- How does resource consumption sequencing affect cost accumulation? (a) Usage patterns determine proper recording order (b) Random recording works fine (c) Sequence remains irrelevant (d) Standard methods fit all helparrow_forward???arrow_forwardCompute production cost per unit under variable costing?arrow_forward
- General Accounting problemarrow_forwardThe balance in the office supplies account on June 1 was $5,200, supplies purchased during June were $2,500, and the supplies on hand at June 30 were $1,500. What is the amount to be used for the appropriate adjusting entry? Provide Answerarrow_forwardCan you help me with accounting questionsarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
How to Estimate Project Costs: A Method for Cost Estimation; Author: Online PM Courses - Mike Clayton;https://www.youtube.com/watch?v=YQ2Wi3Jh3X0;License: Standard Youtube License