City Grow Products is a manufacturer of large flower pots for urban settings. The company has these standards:
Direct materials (resin) | 9.2 pounds per pot at a cost of $4.55 per pound |
Direct labor | 1.6 hours at a cost of $16.60 per hour |
Standard variable manufacturing |
$3.60 per direct labor hour |
Predetermined fixed manufacturing overhead rate | $6.50 per direct labor hour |
City Grow allocates variable and fixed manufacturing overhead to production based on standard direct labor hours.
Requirements
- 1. Compute the standard cost of each of the following inputs per pot: direct materials, direct labor, variable manufacturing overhead, and fixed manufacturing overhead.
- 2. Determine the standard cost of one flower pot.
Expert Solution & Answer

Want to see the full answer?
Check out a sample textbook solution
Students have asked these similar questions
Find out solution for the question
What is the budgeted total cost of direct materials purchases?
Hy expert provide answer with calculation
Chapter 11 Solutions
EBK MANAGERIAL ACCOUNTING
Ch. 11 - (Learning Objective 1) Which of the following is...Ch. 11 - (Learning Objective 2) The direct material price...Ch. 11 - Prob. 3QCCh. 11 - Prob. 4QCCh. 11 - Prob. 5QCCh. 11 - (Learning Objective 4) Which of the following is...Ch. 11 - Prob. 7QCCh. 11 - (Learning Objective 6) Which of the following is...Ch. 11 - Prob. 9QCCh. 11 - (Learning Objective 7Appendix) Which of the...
Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- During September, the assembly department completed 10,500 units of a product that had a standard materials cost of 3.0 square feet per unit at $2.40 per square foot. The actual materials purchased consisted of 22,000 square feet at $2.60 per square foot, for a total cost of $57,200. The actual material used during this period was 25,500 square feet. Compute the materials price variance and materials usage variance.arrow_forwardBluesy Electronics recorded the following financial data: Net Sales $720,500 Average Inventory at Cost = $80,200 Gross Margin Percentage = 42% Calculate the GMROI.arrow_forwardNeed help this question solutionarrow_forward
- XYZ Company has a gross profit margin of 0.30, an operating profit margin of 18%, a total asset turnover ratio of 2.0x, and cost of goods sold of $700,000. The company's tax rate is 35%, and it has no debt. Calculate XYZ Company's Return on Assets (ROA).arrow_forwardMON Pools builds custom swimming pools. MON budgets that they will build 16 pools during the month of June at a price of $22,750 per pool. The actual pools built by MON during June were 13 pools at a price of $23,420 per pool. What is the Flexible Budget Variance for June?arrow_forwardAnderson Corp. pays its employees every Friday for work performed through that Friday. Anderson employees work Monday through Friday and do not work on weekends. The gross payroll for Anderson is $12,500 each week. Anderson will pay its employees $12,500 on Friday, May 8th. This payroll is for wages earned Monday, May 4th through Friday, May 8th. How much of the $12,500 paid on May 8th should be expensed in May?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning

Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license