a)
To determine:
NPV of the project.
Introduction:
The difference between the
a)
Explanation of Solution
Given information:
The initial investment for the project is $67,800,000 and it generates an annual
Explanation:
The given information helps us to conclude that the project has a positive NPV and a very high IRR with initial outflow and subsequent cash inflows. Thus, the project should have a cost of capital less than the IRR value.
b)
To determine:
Cost of capital of the firm.
Introduction:
The difference between the present value of cash inflows and the present value of cash outflows over a period of time is known as the Net Present value. Cost of capital is the cost of long term financing of the firm.
b)
Explanation of Solution
Given information:
The initial investment for the project is $67,800,000 and it generates an annual cash inflow of $30,450,000 for 5 years. The project NPV is $44,200,000 and the IRR is 34.8%.
Explanation:
When the initial investment I0 ,annual cash flow (AC), rate of interest r, and the time period n is given NPV can be calculated using the equation (1) ,
By trial and error method let us assume the cost of capital to be 0.11.
When substituting 11%, NPV is $44,740,064. Since the calculated NPV is greater than the given NPV, increase the interest rate 11.19%.
When the interest rate is 11.19%, the NPV is nearly equal to the given NPV $44,200,000. Thus, cost of capital of the firm is 11.19% (approx..).
c)
To determine:
The payback period of the firm.
Introduction:
Every investment requires a time period to pay back the cost of investment. The time period taken to recover the cost of an investment is known as the payback period.
c)
Explanation of Solution
Given information:
The initial investment for the project is $67,800,000 and it generates an annual cash inflow of $30,450,000 for 5 years. The project NPV is $44,200,000 and the IRR is 34.8%.
Explanation:
Payback period for project can be calculated as follows:
The payback period for project is 2 years and 3 months.
Want to see more full solutions like this?
Chapter 10 Solutions
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
- Perit Industries has $155,000 to invest in one of the following two projects: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A $ 155,000 $ 25,000 $ 8,600 6 1. Net present value project A 2. Net present value project B 3. Which investment alternative (if either) would you recommend that the company accept? X Answer is complete but not entirely correct. Project B $0 $ 155,000 $ 40,000 years The working capital needed for project B will be released at the end of six years for investment elsewhere. Perit Industries' discount rate is 14%. Click here to view Exhibit 14B-1 and Exhibit 14B-2, to determine the appropriate discount factor(s) using tables. Required: 1. Compute the net present value of Project A. Note: Enter negative values with a minus sign. Round your final answer to the nearest whole dollar amount. 2. Compute the net present value of Project B. $(53,971) 70,527 X Project B $0…arrow_forwardThe following information. . Please provide answerarrow_forwardplease answer allarrow_forward
- nku.8arrow_forwardYou are given the following data for a project that is to be evaluated using the APV method. Year EBIT CAPEX Depreciation Increase in NWC Year-end net debt $80,000 O $201.765 O $185,617 O $193,822 0 O$222,872 Cost of net debt-8% Unlevered cost of capital = 11.8% Corporate tax rate = 30% Calculate the total value of the project at t = 0, using the APV method. O $213,918 1 $127,000 $60,000 $72,000 $50,000 $100,000 2 $133,000 $40,000 $80,000 $60,000 $140,000 3 $138,500 $10,000 $84,000 $30,000 $140,000arrow_forwardInformation for two alternative projects involving machinery investments follows: Project 1 Initial investment Salvage value Annual income $ (128,000) Ө Project 2 $ (98,000) 18,000 14,080 11,600 a. Compute accounting rate of return for each project. b. Based on accounting rate of return, which project is preferred? Complete this question by entering your answers in the tabs below. Required A Required B Compute accounting rate of return for each project. Project 1 Project 2 Numerator: Accounting Rate of Return Denominator: Required A Required B Based on accounting rate of return, which project is preferred? Based on accounting rate of return, is preferred. = Accounting rate of returnarrow_forward
- 1. Determine the Net present value of the investment. (use 3 decimal places for the PV factor) 2. Determine the Proposal's internal rate of return 3. Determine the Payback period (3 decimal places)arrow_forwardManubhaiarrow_forwardInformation for two alternative projects involving machinery investments follows: Initial investment Project 1 $ (123,000) Project 2 $ (93,000) Salvage value 0 13,000 Annual income 14,145 12,720 a. Compute accounting rate of return for each project. b. Based on accounting rate of return, which project is preferred? Complete this question by entering your answers in the tabs below. Required A Required B Compute accounting rate of return for each project. Project 1 Project 2 Accounting Rate of Return Denominator: Numerator: 1 = Accounting rate of return 0 0arrow_forward
- You are given the following financial information related to a capital investment project. What is the project's Year 1 Net Cash Flow? Sales revenues Depreciation Other operating costs Interest Exp Tax rate WACC Select one: a. $8,580 b. $8,900 c. $9,350 d. $9,463 e. $9,832 $22,250 $8,000 $12,000 $800 40.0% 12.0%arrow_forwardBella Ltd wishes to invest in either project X or project Y, and has provided you with the following information. Project X Project Y Initial Investment Shs. 20,000 Shs. 30,000 Estimated Life 5 years 5 years Scrap Value Shs. 1,000 Shs. 2,000 The profits before depreciation and after taxation (cash flows) are as follows: Year 1 Year 2 Year 3 Year 4 Year 5 Project x Shs. Shs. Shs. Shs. Shs. 5,000 10,000 10,000 3,000 2,000 Project y 20,000 10,000 5,000 3,000 2,000…arrow_forward: According to the data given in the table below and to the annual equivalent expenditure method, which project should be preferred? Cash flows Project A Project B Project C Investment Amount (TL) 1500000 3475000 5900000 Operating expense (TL / year) Salvage Value (TL) Economic life of the project (years) Discount rate (%) 750000 500000 300000 250000 150000 100000 20 18 15 20 18 15arrow_forward
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub