To determine: The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
a)

Answer to Problem 14P
Explanation of Solution
Given information:
Test | z-score |
Median | +1.37 |
Up/Down | +1.05 |
By observing the given data of median +1.37 (< ±2) and up/down +1.05 (< ±2), it can be concluded that they are within the statistical limits of ±2.
Hence, the result of the run test suggests that the output possess randomness.
b)
To determine: The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
b)

Answer to Problem 14P
Explanation of Solution
Given information:
Formula:
Calculation of expected number of runs:
Observed number of runs = 14
The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 11.
Calculation of standard deviation:
Standard deviation is calculated by subtracting number of sample 20 from 1 and dividing the resultant by 4 and taking square for the value which yields 2.18.
The z factor for median is calculated by dividing the difference of 14 and 11 with 2.18 which yields +1.38 which is within the test statistics of ±2.00 and no non-randomness exist.
Up/Down Test:
The observed number of runs is 8.
Calculation of expected number of runs:
The expected number of runs is calculated by subtracting the double of the number of samples 20 and subtracting from1 and dividing the resultant with 3 which gives 13.
Calculation of standard deviation:
Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.80.
The z factor for median is calculated by dividing the difference of 8 and 13 with 1.80 which yields -2.78 which is beyond the test statistics of ±2.00 which is non-random.
Hence, the result of the median run test is random and up/down test is no non randomness is detected.
c)
To determine: The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
c)

Answer to Problem 14P
Explanation of Solution
Given information:
Cable | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
Defects | 2 | 3 | 1 | 0 | 1 | 3 | 2 | 0 | 2 | 1 | 3 | 1 | 2 | 0 |
Formula:
Analysis of data:
To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,
Median run test:
From analysis, the observed number of runs is 10 and median is 1.5.
Calculation of expected number of runs:
The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.
Calculation of standard deviation:
Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.
The z factor for median is calculated by dividing the difference of 10 and 8 with 1.80 which yields +1.11 which is within the test statistics of ±2.00 and no non-randomness exist.
Up/Down Test:
The observed number of runs from the analysis is 10.
Calculation of expected number of runs:
The expected number of runs is calculated by subtracting the double of the number of samples 14 and subtracting from1 and dividing the resultant with 3 which gives 9.0.
Calculation of standard deviation:
Standard deviation is calculated by multiplying the number of samples with 14 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.
The z factor for median is calculated by dividing the difference of 10 and 9 with 1.47 which yields +0.68which is within the test statistics of ±2.00.
Hence, the results of the median run test and up/down test is random and no non randomness is detected.
d)
To determine:The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
d)

Answer to Problem 14P
Explanation of Solution
Given information:
Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
Comp. | 4 | 10 | 14 | 8 | 9 | 6 | 5 | 12 | 13 | 7 | 6 | 4 | 2 | 10 |
Formula:
Analysis of data:
To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,
Median run test:
From analysis, the observed number of runs is 8.
Calculation of expected number of runs:
The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.
Calculation of standard deviation:
Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.
The z factor for median is calculated by dividing the difference of 6 and 8 with 1.80 which yields -1.11 which is beyond the test statistics of ±2.00 and non-randomness exist.
Up/Down Test:
The observed number of runs from the analysis is 7.
Calculation of expected number of runs:
The expected number of runs is calculated by subtracting the double of the number of samples 26 and subtracting from1 and dividing the resultant with 3 which gives 9.0.
Calculation of standard deviation:
Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.
The z factor for median is calculated by dividing the difference of 7 and 9 with 1.47 which yields -1.36 which is within the test statistics of ±2.00.
Hence, the results of the median run test and up/down test is random and no non randomness is detected.
Want to see more full solutions like this?
Chapter 10 Solutions
EBK OPERATIONS MANAGEMENT
- >>>> G סוי - C Mind Tap Cengage Learning CENGAGE MINDTAP Chapter 12 Homework: Managing Inventories in Supply Chains Questions Problem 12-44 Algo (Managing Fixed-Quantity Inventory Systems) 1. e 2. 3. 自 4. 5. ? ↑ 6. 7. 8. 9. 10. 11. ng.cengage.com + O C Excel Online Student Work Q Search this course ? Question 3 of 11 ► Hint(s) Check My Work Brenda opened a pool and spa store in a lively shopping mall and finds business to be booming but she often stocks out of key items customers want. The 28-ounce bottle of Super Algaecide (SA) is a high margin SKU, but it stocks out frequently. Ten SA bottles come in each box, and she orders boxes from a vendor 160 miles away. Brenda is busy running the store and seldom has time to review store inventory status and order the right quantity at the right time. She collected the following data: Demand = 9 boxes per week Order cost = $90/order Store open = 48 weeks/year Lead-time = 3 weeks Item cost = $180/box Inventory-holding cost = 10 percent per…arrow_forwardווח CENGAGE MINDTAP G Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 A e Submit 自 ? G→ Video Excel Online Tutorial Excel Online Activity: Exponential Smoothing ng.cengage.com Q Search this course ? A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 91.01 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 23.50 3. Choose the correct graph for the single exponential smoothing forecast. The correct graph is graph A ☑ Back Observation Exponential Smoothing Forecast 100 Forecast 95 95 90 90 A-Z Office Next A+arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A Time B- Code Description (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 20 None B Requisition of lumber and sand 65 A C Dig and grade 100 A D Saw lumber into appropriate sizes 30 B E Position lumber in correct locations 25 D, C F Nail lumber together E G Put sand in and under the equipment 25 F H H Put dirt around the equipment 10 F Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 0 20 40 60 80 100 120 140 160 180 200 220 Clear allarrow_forward
- List three forms of pay you receive (not dollar amounts). Compare your list to two of your peers. Discuss any differences or similarities that you noticed. NO AIarrow_forwardPlease and thank youarrow_forwardA local fast-food restaurant processes several customer orders at once. Service clerks’ cross paths, sometimes nearly colliding, while they trace different paths to fill customer orders. If customers order a special combination of toppings on their burgers, they must wait quite some time while the special order is cooked. How would you modify the restaurant’s operations to achieve competitive advantage? Because demand surges at lunchtime, volume flexibility is a competitive priority in the fast-food business. How would you achieve volume flexibility? What are the potential downsides of relying too heavily on automation and standardization in this industry? What data would you want to gather, if any, before making recommendations?arrow_forward
- What are 4 key points that are interesting about this video https://youtu.be/LAoMuvYZ_QM?si=Mognj_KBU9EIOLSParrow_forwarda) Select all of the correct impacts the maturing of a product might have on OM strategy below. (Check all that apply.) A. Cost cutting is instituted. B. Inventory needs to be revised. C. Labor skills decrease. D. Product design needs to be revised. E. Design compromises are instituted. F. New human resources skills.arrow_forwardPlease help! Multifactor!arrow_forward
- Klassen Toy Company, Inc., assembles two parts (parts 1 and 2): Part 1 is first processed at workstation A for 10 minutes per unit and then processed at workstation B for 20 minutes per unit. Part 2 is simultaneously processed at workstation C for 12 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are assembled. The time at workstation D is 15 minutes. a) The bottleneck of this process is at minutes per unit (enter your response as a whole number).arrow_forwardJust HELParrow_forwardI need help with C. I'm strugglingarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,