Question
Book Icon
Chapter 10, Problem 14P

a)

Summary Introduction

To determine: The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

a)

Expert Solution
Check Mark

Answer to Problem 14P

The result of the run test suggests that the output possess randomness.

Explanation of Solution

Given information:

Test z-score
Median +1.37
Up/Down +1.05

By observing the given data of median +1.37 (< ±2) and up/down +1.05 (< ±2), it can be concluded that they are within the statistical limits of ±2.

Hence, the result of the run test suggests that the output possess randomness.

b)

Summary Introduction

To determine: The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

b)

Expert Solution
Check Mark

Answer to Problem 14P

The results of the median run test and up/down test is random and no non randomness is detected.

Explanation of Solution

Given information:

Numberofmeans=20Numberofrunscountedabove/below=14Numberofrunscountedup/down=8

Formula:

Ztest=Observed-ExpectedStandarddeviation

Calculation of expected number of runs:

Observed number of runs = 14

E(r)med=N2+1=202+1=11.0

The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 11.

Calculation of standard deviation:

σmed=N14=2014=2.18

Standard deviation is calculated by subtracting number of sample 20 from 1 and dividing the resultant by 4 and taking square for the value which yields 2.18.

Ztest=14-112.18=+1.38

The z factor for median is calculated by dividing the difference of 14 and 11 with 2.18 which yields +1.38 which is within the test statistics of ±2.00 and no non-randomness exist.

Up/Down Test:

The observed number of runs is 8.

Calculation of expected number of runs:

E(r)u/d=2N13=(2×20)13=13.0

The expected number of runs is calculated by subtracting the double of the number of samples 20 and subtracting from1 and dividing the resultant with 3 which gives 13.

Calculation of standard deviation:

σu/d=16N2990=(16×20)2990=1.80

Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.80.

Ztest=8-13.01.80=2.78

The z factor for median is calculated by dividing the difference of 8 and 13 with 1.80 which yields -2.78 which is beyond the test statistics of ±2.00 which is non-random.

Hence, the result of the median run test is random and up/down test is no non randomness is detected.

c)

Summary Introduction

To determine: The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

c)

Expert Solution
Check Mark

Answer to Problem 14P

The results of the median run test and up/down test is random and no non randomness is detected.

Explanation of Solution

Given information:

Cable 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Defects 2 3 1 0 1 3 2 0 2 1 3 1 2 0

Formula:

Ztest=Observed-ExpectedStandarddeviation

Analysis of data:

EBK OPERATIONS MANAGEMENT, Chapter 10, Problem 14P , additional homework tip  1

c¯=2114=1.5

To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,

Median run test:

From analysis, the observed number of runs is 10 and median is 1.5.

Calculation of expected number of runs:

E(r)med=N2+1=142+1=8.0

The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.

Calculation of standard deviation:

σmed=N14=1414=1.80

Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.

Ztest=10-81.80=+1.11

The z factor for median is calculated by dividing the difference of 10 and 8 with 1.80 which yields +1.11 which is within the test statistics of ±2.00 and no non-randomness exist.

Up/Down Test:

The observed number of runs from the analysis is 10.

Calculation of expected number of runs:

E(r)u/d=2N13=(2×14)13=9.0

The expected number of runs is calculated by subtracting the double of the number of samples 14 and subtracting from1 and dividing the resultant with 3 which gives 9.0.

Calculation of standard deviation:

σu/d=16N2990=(16×14)2990=1.47

Standard deviation is calculated by multiplying the number of samples with 14 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.

Ztest=10-9.01.47=+0.68

The z factor for median is calculated by dividing the difference of 10 and 9 with 1.47 which yields +0.68which is within the test statistics of ±2.00.

Hence, the results of the median run test and up/down test is random and no non randomness is detected.

d)

Summary Introduction

To determine:The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

d)

Expert Solution
Check Mark

Answer to Problem 14P

The results of the median run test and up/down test is random and no non randomness is detected.

Explanation of Solution

Given information:

Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Comp. 4 10 14 8 9 6 5 12 13 7 6 4 2 10

Formula:

Ztest=Observed-ExpectedStandarddeviation

Analysis of data:

EBK OPERATIONS MANAGEMENT, Chapter 10, Problem 14P , additional homework tip  2

c¯=11014=7.875

To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,

Median run test:

From analysis, the observed number of runs is 8.

Calculation of expected number of runs:

E(r)med=N2+1=142+1=8.0

The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.

Calculation of standard deviation:

σmed=N14=1414=1.80

Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.

Ztest=6-81.80=1.11

The z factor for median is calculated by dividing the difference of 6 and 8 with 1.80 which yields -1.11 which is beyond the test statistics of ±2.00 and non-randomness exist.

Up/Down Test:

The observed number of runs from the analysis is 7.

Calculation of expected number of runs:

E(r)u/d=2N13=(2×14)13=9.0

The expected number of runs is calculated by subtracting the double of the number of samples 26 and subtracting from1 and dividing the resultant with 3 which gives 9.0.

Calculation of standard deviation:

σu/d=16N2990=(16×14)2990=1.47

Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.

Ztest=7-9.01.47=1.36

The z factor for median is calculated by dividing the difference of 7 and 9 with 1.47 which yields -1.36 which is within the test statistics of ±2.00.

Hence, the results of the median run test and up/down test is random and no non randomness is detected.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Consider the nonlinear optimization model stated below. Min 2x²-18x + 2XY + y² 14Y + 51 s.t. X + 4Y ≤7 (a) Find the minimum solution to this problem. at (X, Y) = (b) If the right-hand side of the constraint is increased from 7 to 8, how much do you expect the objective function to change? Based on the dual value on the constraint X + 4Y ≤7, we expect the optimal objective function value to decrease by (c) Resolve the problem with a new right-hand side of the constraint of 8. How does the actual change compare with your estimate? If we resolve the problem with a new right-hand-side of 8 the new optimal objective function value is , so the actual change is a decrease of rather than what we expected in part (b).
Burger Dome sells hamburgers, cheeseburgers, french fries, soft drinks, and milk shakes, as well as a limited number of specialty items and dessert selections. Although Burger Dome would like to serve each customer immediately, at times more customers arrive than can be handled by the Burger Dome food service staff. Thus, customers wait in line to place and receive their orders. Burger Dome analyzed data on customer arrivals and concluded that the arrival rate is 40 customers per hour. Burger Dome also studied the order-filling process and found that a single employee can process an average of 56 customer orders per hour. Burger Dome is concerned that the methods currently used to serve customers are resulting in excessive waiting times and a possible loss of sales. Management wants to conduct a waiting line study to help determine the best approach to reduce waiting times and improve service. Suppose Burger Dome establishes two servers but arranges the restaurant layout so that an…
>>>> e 自 A ? ↑ G סוי - C Mind Tap Cengage Learning CENGAGE MINDTAP Chapter 12 Homework: Managing Inventories in Supply Chains Assignment: Chapter 12 Homework: Managing Inventories in Supply Chains Questions Problem 12-70 Algo (Managing Fixed-Quantity Inventory Systems) 6. 7. ng.cengage.com + O C Excel Online Student Work Q Search this course ? Save Assignment Score: 91.34% Submit Assignment for Grading e Question 8 of 11 ▸ A-Z Hint(s) Check My Work 8. 9. 10. 11. Spreadsheet Environmental considerations, material losses, and waste disposal can be included in the EOQ model to improve inventory-management decisions. Assume that the annual demand for an industrial chemical is 1,600 lb, item cost is $2/lb, order cost is $45, inventory holding cost rate (percent of item cost) is 15 percent. Use the EOQ Model Excel template in MindTap to answer the following: a. Find the EOQ and total cost, assuming no waste disposal. Do not round intermediate calculations. Round your answer for the EOQ to…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L