Chapter 1, Problem 5QQ
Program Description Answer
Meeting communication goals is not a part of the triple constraint of project management.
Hence, correct answer is option “C”.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
If there are constant, regular changes to the scope of the IT project, there may come a time when
the decision is made to rethink both resource allocation and project success criteria. This is
known as...
a. Scope creep
b. Scope grope
c. Scope leap
d. Scope validation
Key stakeholders will be required to agree on the business case and project charter. This helps
establish the...
a. Product scope
b. Project scope
c. Project scope change process
d. Project methodology
What activity is performed in the beginning during the formation of a project team?
a. Identify the objectives
b. The selection of team members
c. Allocation of resources are identified
d. The stakeholders are committed to the project
Chapter 1 Solutions
Mindtap For Schwalbe's Information Technology Project Management, 1 Term Printed Access Card
Ch. 1 - Why is there a new or renewed interest in the...Ch. 1 - Prob. 2DQCh. 1 - What is project management? Briefly describe the...Ch. 1 - What is a program? What is a project portfolio?...Ch. 1 - What is the role of the project manager? What are...Ch. 1 - Briefly describe some key events in the history of...Ch. 1 - Prob. 7DQCh. 1 - Discuss ethical decisions that project managers...Ch. 1 - Prob. 1QQCh. 1 - Prob. 2QQ
Ch. 1 - Prob. 3QQCh. 1 - Prob. 4QQCh. 1 - Prob. 5QQCh. 1 - _____ is the application of knowledge, skills,...Ch. 1 - Prob. 7QQCh. 1 - Several application development projects done for...Ch. 1 - Prob. 9QQCh. 1 - Prob. 10QQCh. 1 - Read at least two of the first five references...Ch. 1 - Prob. 2ECh. 1 - Prob. 3ECh. 1 - Prob. 4ECh. 1 - Prob. 5ECh. 1 - Research articles and tools on project portfolio...Ch. 1 - Prob. 7ECh. 1 - Research information about PMP® and CAPM®...Ch. 1 - Review PMI’s Code of Ethics and Professional...
Knowledge Booster
Similar questions
- A work breakdown structure, project schedule, and cost estimates are outputs of the ____________ process. initiating planning executing monitoring and controlling closingarrow_forwardWrite a short paper based on the chapters opening case. Answer the following questions: a. What do you think the real problem was in this case? b. Does the case present a realistic scenario? Why or why not? c. Was Nick Carson a good project manager? Why or why not? d. What should top management have done to help Nick? e. What could Nick have done to be a better project manager?arrow_forwardWhich of the following processes is not part of project integration management? a. Developing the project business case b. Developing the project charter c. Developing the project management plan d. Closing the project or phasearrow_forward
- What is the value of a statement of vision and objectives? Why is it needed before a project plan is developed?arrow_forwardThe ____________ is a key member and the leader of the steering team who plays such a critical role that lack of this essential individual raises the possibility of project failure.arrow_forwardWhy do you need a good WBS to use project management software? What other types of software can you use to assist in project scope management?arrow_forward
- A project has been defined to contain the following list of activities along with their required times for completion: Construct Gantt Chart, Network Diagram and Critical Path for the below chart: Immediate Activity No. Predecessors ABCDEFGHI Activity Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and Document Install Time (weeks) 3 2447NWONN 6 3 5 A B B C C,D D,E F,G G H₁Iarrow_forwardcompare and contract the scrum approach to project management with conventional plan-based approaches as discussed in Chapter 23. Your comparison should be based on the effectiveness of each approach for planning the allocation of people to projects, estimating the cost of projects, maintaining team cohesion, and managing changes in project team membership.arrow_forward10 Which of the following is a classic organizational structure? A Functional B Projectized C Composite D Matrix 11 Defining a new project or a new phase of an existing project relates to A Initiating process. B. Planning process C Scope management process D. Control process 12 If you are developing a Project Management Plan, how should you determine the level of detail to be included in the plan? A Always only provide a summary or high level plan B Include only the details your manager specifically requested C Always provide the maximum level of detail possible D. Provide the level of detail based on the project complexity and application area 13 Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied? A. Crashing B. Reserve Analysis C. Forecasting D. Last Tracking 14.…arrow_forward
- In which project management phase is the scope of the work defined? a. Initiating b. Planning O c. Executing d. Closingarrow_forwardAnswer the following questions based on project planning Software Engineering: 1. Explain the looping process that occurs from the project scheduling! What criteria can be used to assume the loop process can be terminated?2. What is the difference between forward scheduling and backward scheduling, use the example [https://iansommerville.com/software-engineering-book/web/planning-activities/]? Also compare the Critical Path results of the two scheduling approaches?3. Is there a difference in Release Planning vs. Iteration Planning in making software using an Agile approach?4. Explain the level of accuracy of the Project Cost Estimation with COCOMO II?5. Explain how to get the estimated source line of code (SLOC)?arrow_forwardProject viability criteria must be compiled and discussed. Is there a determining factor? Why?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Security (MindTap Cours...Computer ScienceISBN:9781337102063Author:Michael E. Whitman, Herbert J. MattordPublisher:Cengage Learning
- Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningFundamentals of Information SystemsComputer ScienceISBN:9781337097536Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning