EBK INFORMATION TECHNOLOGY PROJECT MANA
EBK INFORMATION TECHNOLOGY PROJECT MANA
8th Edition
ISBN: 9781337431095
Author: SCHWALBE
Publisher: YUZU
Expert Solution & Answer
Book Icon
Chapter 1, Problem 5QQ
Program Description Answer

Meeting communication goals is not a part of the triple constraint of project management.

Hence, correct answer is option “C”.

Blurred answer
Students have asked these similar questions
I need help making this EER diagram in Chen Notation.
In Java I have an input in a text file that I can't submit here. So, please use it as input.txt
Perceptual acuity, according to Ram Charan, explains how Ted Turner became the first CEO to recognize the potential of 24-hour news and thereby created CNN. a) True  b) False
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning