Concept explainers
a)
To determine: The multifactor productivity for last year.
Introduction: Multifactor productivity is an evaluation of economic performance that compares the amount of products and services produced to the amount of combined inputs used to produce those products and services.
a)

Answer to Problem 17P
Hence, the multifactor productivity for last year is 0.8533.
Explanation of Solution
Given information:
The given information is as follows:
Last year | This year | |
Production (dozen) | 1,500 | 1,500 |
Labor (hours) | 350 | 325 |
Capital investment ($) | 15,000 | 18,000 |
Energy (BTU) | 3,000 | 2,700 |
Labor cost is given as $8 per hour, capital is 0.83% per month of investment, and energy is $0.60 per BTU.
Formulae to determine the multifactor productivity:
Determine the multifactor productivity for last year:
It is calculated by dividing the output units and the value attained by adding the multiple of labor hours and cost per hours, sum of capital investment and interest on capital, and multiple of energy and rate.
Hence, the multifactor productivity for last year is 0.8533.
b)
To determine: The multifactor productivity for the current year.
Introduction: Multifactor productivity is an evaluation of economic performance that compares the amount of products and services produced to the amount of combined inputs used to produce those products and services.
b)

Answer to Problem 17P
Hence, the multifactor productivity for this year is 0.7496.
Explanation of Solution
Given information:
The given information is as follows:
Last year | This year | |
Production (dozen) | 1,500 | 1,500 |
Labor (hours) | 350 | 325 |
Capital investment ($) | 15,000 | 18,000 |
Energy (BTU) | 3,000 | 2,700 |
Labor cost is given as $8 per hour, capital is 0.83% per month of investment, and energy is $0.60 per BTU.
Formulae to determine the multifactor productivity:
Determine the multifactor productivity for this year:
It is calculated by dividing the output units and the value attained by adding the multiple of labor hours and cost per hours, sum of capital investment and interest on capital, and multiple of energy and rate.
Hence, the multifactor productivity for this year is 0.7496.
c)
To determine: The percentage change in productivity for the monthly average last year versus the monthly average this year.
Introduction: Productivity is a measure of the effectiveness of an individual, systems, machinery and other equipment that are used in converting inputs into outputs. In all organizations, productivity is an important determinant to know cost efficiency.
c)

Answer to Problem 17P
Hence, the percent change in multifactor productivity last year versus this year is -11.764.
Explanation of Solution
Given information:
The given information is as follows:
Last year | This year | |
Production (dozen) | 1,500 | 1,500 |
Labor (hours) | 350 | 325 |
Capital investment ($) | 15,000 | 18,000 |
Energy (BTU) | 3,000 | 2,700 |
Labor cost is given as $8 per hour, capital is 0.83% per month of investment, and energy is $0.60 per BTU.
Formulae to calculate the percentage change on multifactor basis:
Calculate the percentage change on multifactor basis:
It is calculated by the dividing the value attained by subtracting the multifactor productivity last year from last year from this year and the multifactor productivity last year.
Hence, the percentage change on multifactor basis is -12.15%.
Want to see more full solutions like this?
Chapter 1 Solutions
Principles Of Operations Management
- provide scholarly reseach and define legal and complince risk and reputational risk in banking. Additionally 1. What more can be done about it 2. the department where the risk is exposed to 3. what strategy can be used 4. responsible personarrow_forwardRead the case in the link below and Develop a risk management programme appropriate for this case using the attached template. https://finopsinfo.com/investors/citis-900m-blunder-casts-light-on-poor-loan-ops/arrow_forwardDo the inherent differences between private and public sector objectives—profit versus publicgood—render private sector category management practices unsuitable for public sectorpurchasing, where open tendering is the norm?You have now undergone the Category Management classes and your superiors have requestedfor your input on how to integrate some of the learnings into the public sector policy. Discuss and elaborate what are the activities and governance you would introduce in yourrecommendations without violating the principle of transparency and accountability withinyour organisation. This is based on Singapore context. Pls provide a draft with explanation, examples and useful links for learning purposes. Citations will be good too. This is a module in SUSS called category management and supplier evaluationarrow_forward
- provide scholarly answers for what risk was associated with the Citibank bank loosing 50 million in August 2020arrow_forwardConclusion: The report recommendations and broad conclusion to the essay. TOTAL 5 100arrow_forwardAs part of your new role, as a strategy consultant and member of the steering committee, discuss what logistics and transportation strategies you will execute to achieve operational efficiencies and facilitate economic growth in SA. The committee would like to have a implementable strategic transport and logistics plan to realise the roadmap vision based on the subsection numbering given below! QUESTION ONE Introduction: Must include an overview and history of South Africa's Road, rail and freight transport network. Marks 5arrow_forward
- 1.2 What are the current freight and logistic challenges on the road network 10 1.3 Discuss key relevant financials of infrastructure, industries and revenue resulting in this logistics crisis. 15arrow_forwardAs part of your new role, as a strategy consultant and member of the steering committee, discuss what logistics and transportation strategies you will execute to achieve operational efficiencies and facilitate economic growth in SA. The committee would like to have a implementable strategic transport and logistics plan to realise the roadmap vision based on the subsection numbering given below: QUESTION ONE Marks 5 Introduction: Must include an overview and history of South Africa's Road, rail and freight transport network. 1.1 Assess what led to such logistical inefficiencies/collapse of a previously world class freight network 10 1.2 What are the current freight and logistic challenges on the road network 10 1.3 Discuss key relevant financials of infrastructure, industries and revenue resulting in this logistics crisis. 15 1.4 Discuss how the key stakeholder partnerships - current and future are critical to government and business as part of the overall intermodal transport strategy.…arrow_forwardWhat are the current freight and logistic challenges on the road network Discuss key relevant financials of infrastructure, industries and revenue resulting in this logistics crisis. 10 15arrow_forward
- 1.5 If you examine the freight supply and value chain, what transport and infrastructure strategies and 25 plans need to be implemented to improve operation efficiencies and reduce costs. 5 1.6 15 Discuss how implementation of a strategic intermodal transport plan can further unlock and improve South Africa's GDP and international recognition.arrow_forwardA certain business process is no longer providing the desired benefits, therefore it needs to be re-designed through a project. You have to: Choose the business process to re-design and specify the reason why it is no longer satisfactory. Ask ChatGPT (or a similar generative AI; specify name and version) to create a Project Charter for the process redesign project. Modify and refine the response provided by the AI tool ensuring it complies with the instructor’s lesson, with particular focus on the project goals, project objectives, and deliverables (remember: project objectives must be SMART!). Your work must be delivered in the following format: a)Describe the business process to re-design (example: “The process of hiring and integrating new employees into the Sales Administration department”. Do not exceed 20 words) b)Specify the reason to re-design the business process which is already in place (describe the reason why the current process is no longer satisfactory, for…arrow_forwardThe demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers). Item 1 2 3 Week 4 Lead Time 5 6 7 (weeks) S Gross req On hand Net req Order receipt Order release T Gross req On hand Net req Order receipt Order release Gross rea 100 100arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub