You work for the Brad's Nailer Company which manufactures two types of nailers: a pneumatic model and a cordless model. You have contracted to supply a national retail chain with both pneumatic nailers and cordless nailers. However, Brad's nailer production capability is limited in three departments: production, testing, and packaging. Your answer will be the testing hours needed to execute your production plan - rounded to the nearest whole hour. (The number of nailers must be a whole number.) Use Scenario 3 Scenario 1 Scenario 2 Scenario 3 Pneum. Cost 69.14 55.50 38.50 Pneum. Prod Hrs 0.75 0.6 0.35 Pneum. Test Hrs 0.4 0.35 0.4 Pneum. Pkg Hrs 0.1 0.2 0.1 Pneum. Sales 7,800 24,500 18.000 Cordless Cost 74.45 69.75 44 Cordless Prod Hrs 0.8 0.7 0.4 Cordless Test Hrs 0.4 0.4 0.4 Cordless Pkg Hrs 0.15 0.25 0.2 Cordless Sales 10.500 15.500 14.000 Prod Hrs max 20,000 30.000 20.000 Testing Hrs max 9.000 15.000 18.000 Pkg Hrs max 5.000 15.000 5.000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
1...
Adidas "Anthem" 0..
Club America FC y...
Read
20
You work for the Brad's Nailer Company which manufactures
two types of nailers: a pneumatic model and a cordless
model. You have contracted to supply a national retail chain
with both pneumatic nailers and cordless nailers. However,
Brad's nailer production capability is limited in three
departments: production, testing, and packaging.
Your answer will be the testing hours needed to execute your
production plan - rounded to the nearest whole hour. (The
number of nailers must be a whole number.)
Use Scenario 3
Scenario 1 Scenario 2 Scenario 3
Pneum. Cost
69.14
55.50
38.50
Pneum. Prod Hrs 0.75
0.6
0.35
Pneum. Test Hrs
0.4
0.35
0.4
Pneum. Pkg Hrs
0.1
0.2
0.1
Pneum. Sales
7.800
24,500
18,000
Cordless Cost
74.45
69.75
44
Cordless Prod Hrs 0.8
0.7
0.4
Cordless Test Hrs 0.4
0.4
0.4
Cordless Pkg Hrs 0.15
0.25
0.2
Cordless Sales
10,500
15.500
14.000
Prod Hrs max
20.000
30.000
20.000
Testing Hrs max
9.000
15.000
18.000
Pkg Hrs max
5.000
15.000
5.000
Transcribed Image Text:1... Adidas "Anthem" 0.. Club America FC y... Read 20 You work for the Brad's Nailer Company which manufactures two types of nailers: a pneumatic model and a cordless model. You have contracted to supply a national retail chain with both pneumatic nailers and cordless nailers. However, Brad's nailer production capability is limited in three departments: production, testing, and packaging. Your answer will be the testing hours needed to execute your production plan - rounded to the nearest whole hour. (The number of nailers must be a whole number.) Use Scenario 3 Scenario 1 Scenario 2 Scenario 3 Pneum. Cost 69.14 55.50 38.50 Pneum. Prod Hrs 0.75 0.6 0.35 Pneum. Test Hrs 0.4 0.35 0.4 Pneum. Pkg Hrs 0.1 0.2 0.1 Pneum. Sales 7.800 24,500 18,000 Cordless Cost 74.45 69.75 44 Cordless Prod Hrs 0.8 0.7 0.4 Cordless Test Hrs 0.4 0.4 0.4 Cordless Pkg Hrs 0.15 0.25 0.2 Cordless Sales 10,500 15.500 14.000 Prod Hrs max 20.000 30.000 20.000 Testing Hrs max 9.000 15.000 18.000 Pkg Hrs max 5.000 15.000 5.000
Expert Solution
Step 1: Decision variables

P = Pneum. Units to be produced

C = Cordless Units to be produced

Objective function:

Min Z = 38.50P+44C

Constraints:

1. Production hours: 0.35P+0.40C20000

2. Test hours: 0.4P+0.4C18000

3. Packaging hours: 0.1P+0.2C5000

4. Pneum. production: P18000

5. Cordless production: C14000

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.