You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started. Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will perform. The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components together, and a working prototype is built and tested. Finally, in subproject "V" suppliers are selected and contracts are negotiated. Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project ACTIVITY IDENTIFICATION MAJOR SUBPROJECTS/ACTIVITIES Product Specifications (P) Market research. Overall product specifications Hardware Software. Supplier specifications (S) Product design (D) Product integration (I) Hardware Software Subcontracting (V) Battery Display Camera Outer cover Hardware User interface. Software coding Prototype testing Suppliers selection. Contract negotiation. P1 OD O AN SS P2 P3 P4 S1 S2 D1 D2 D3 D4 11 I2 13 14 V1 V2 DEPENDENCY P1 P2 P3 P4 P4 S1 51 $1 D1, D2, D3 D4 D2 12 11, 13 $1,52 14, V1 DURATION (WEEKS) 2 4 5 5 5 6 1 2 1 4 3 4 4 4 10 2 Identify slack in the activities not on the project critical path. (Leave no cells blank - be certain to enter "0" wherever required.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Q222
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your
supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project
activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow
morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each
activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully
completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here,
decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a
customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will
actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will
perform.
The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components
together, and a working prototype is built and tested.
Finally, in subproject "V," suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES
Product Specifications (P)
Market research.
Overall product specifications
Hardware
Software.
Supplier specifications (S)
Product design (D)
Product integration (I)
Subcontracting (V)
Hardware.
Software
Battery
Display
Cameral
Outer cover
Hardware
User interface
Software coding
Prototype testing
Activity ID Slack
Suppliers selection.
Contract negotiation
ACTIVITY IDENTIFICATION
P1
SS UNE BOND SPEND
$1
S2
D1
DEPENDENCY
ı ៩ ៩ ៩ ៩ ៨ ៨ ៨៩ ៩៩ ៨
P3
P4
P4
S1
51
D1, D2, D3
11, 13
S1,S2
14, V1
DURATION (WEEKS)
2
4
5
5
5
6
1
2
1
4
3
4
4
4
10
2
Identify slack in the activities not on the project critical path. (Leave no cells blank - be certain to enter "0" wherever required.)
Transcribed Image Text:You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started. Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will perform. The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components together, and a working prototype is built and tested. Finally, in subproject "V," suppliers are selected and contracts are negotiated. Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project MAJOR SUBPROJECTS/ACTIVITIES Product Specifications (P) Market research. Overall product specifications Hardware Software. Supplier specifications (S) Product design (D) Product integration (I) Subcontracting (V) Hardware. Software Battery Display Cameral Outer cover Hardware User interface Software coding Prototype testing Activity ID Slack Suppliers selection. Contract negotiation ACTIVITY IDENTIFICATION P1 SS UNE BOND SPEND $1 S2 D1 DEPENDENCY ı ៩ ៩ ៩ ៩ ៨ ៨ ៨៩ ៩៩ ៨ P3 P4 P4 S1 51 D1, D2, D3 11, 13 S1,S2 14, V1 DURATION (WEEKS) 2 4 5 5 5 6 1 2 1 4 3 4 4 4 10 2 Identify slack in the activities not on the project critical path. (Leave no cells blank - be certain to enter "0" wherever required.)
Product integration (I)
Subcontracting (V)
Activity ID
P1
P2
P3
P4
S1
S2
D1
D2
D3
D4
11
12
13
14
V1
V2
Display
Camera
Outer cover
Hardware
User interface
Software coding
Prototype testing
Suppliers selection
Contract negotiation
Slack
28 EAN 5S
D2
D3
D4
I1
12
13
14
V1
V2
S1
S1
D1, D2, D3
8802
D4
D2
12
11, 13
S1,S2
14, V1
2
1
Identify slack in the activities not on the project critical path. (Leave no cells blank - be certain to enter "0" wherever required.)
4
3
4
4
4
10
2
Transcribed Image Text:Product integration (I) Subcontracting (V) Activity ID P1 P2 P3 P4 S1 S2 D1 D2 D3 D4 11 12 13 14 V1 V2 Display Camera Outer cover Hardware User interface Software coding Prototype testing Suppliers selection Contract negotiation Slack 28 EAN 5S D2 D3 D4 I1 12 13 14 V1 V2 S1 S1 D1, D2, D3 8802 D4 D2 12 11, 13 S1,S2 14, V1 2 1 Identify slack in the activities not on the project critical path. (Leave no cells blank - be certain to enter "0" wherever required.) 4 3 4 4 4 10 2
Expert Solution
Given details:

Find the Given details below:

Activity Dependency Duration (Weeks)
P1 - 2
P2 P1 4
P3 P2 5
P4 P3 5
S1 P4 5
S2 P4 6
D1 S1 1
D2 S1 2
D3 S1 1
D4 D1, D2,D3 4
I1 D4 3
I2 D2 4
I3 I2 4
I4 I1, I3 4
V1 S1, S2 10
V2 I4, V1 2
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.