You should accept a project when the ?: net present value is negative. profitability index is positive. payback period exceeds the required period. AAR is greater than the required return. 7. Which one of the following statements is correct? The payback period is also referred to as the benefit-cost ratio. The internal rate of return can be reliably used for all independent projects. The profitability index is used when the investment funds are limited. The net present value should not be used to rank mutually exclusive projects. 8. You should accept a project when the ?: net present value is negative. profitability index is less than 1 but greater than 0. discounted payback period is less than the required period. AAR is less than the required return. 9. The crossover point ? : is used to determine which one of two internal rates of return for a project should be used when determining if a project should be accepted. 2. is the point where the net present value of a project is equal to 0. 3. equates the net present values of two separate projects. 4. is the point in time when a project pays back on a discounted basis. 10. Which one of the following statements is correct? The payback period of a project will be longer than the discounted payback period. The internal rate of return can be reliably used for all independent projects. The internal rate of return is used to evaluate different sized projects. The internal rate of return should not be used to rank mutually exclusive projects.
You should accept a project when the ?: net present value is negative. profitability index is positive. payback period exceeds the required period. AAR is greater than the required return. 7. Which one of the following statements is correct? The payback period is also referred to as the benefit-cost ratio. The internal rate of return can be reliably used for all independent projects. The profitability index is used when the investment funds are limited. The net present value should not be used to rank mutually exclusive projects. 8. You should accept a project when the ?: net present value is negative. profitability index is less than 1 but greater than 0. discounted payback period is less than the required period. AAR is less than the required return. 9. The crossover point ? : is used to determine which one of two internal rates of return for a project should be used when determining if a project should be accepted. 2. is the point where the net present value of a project is equal to 0. 3. equates the net present values of two separate projects. 4. is the point in time when a project pays back on a discounted basis. 10. Which one of the following statements is correct? The payback period of a project will be longer than the discounted payback period. The internal rate of return can be reliably used for all independent projects. The internal rate of return is used to evaluate different sized projects. The internal rate of return should not be used to rank mutually exclusive projects.
Managerial Accounting: The Cornerstone of Business Decision-Making
7th Edition
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Chapter12: Capital Investment Decisions
Section: Chapter Questions
Problem 16MCQ: Using IRR, a project is rejected if the IRR a. is equal to the required rate of return. b. is less...
Related questions
Question
You should accept a project when the ?:
net present value is negative.- profitability index is positive.
- payback period exceeds the required period.
- AAR is greater than the required return.
7. Which one of the following statements is correct?
- The payback period is also referred to as the benefit-cost ratio.
- The
internal rate of return can be reliably used for all independent projects. - The profitability index is used when the investment funds are limited.
- The net present value should not be used to rank mutually exclusive projects.
8. You should accept a project when the ?:
- net present value is negative.
- profitability index is less than 1 but greater than 0.
- discounted payback period is less than the required period.
- AAR is less than the required return.
9. The crossover point ? :
- is used to determine which one of two internal
rates of return for a project should be used
when determining if a project should be accepted.
2. is the point where the net present value of a project is equal to 0.
3. equates the net present values of two separate projects.
4. is the point in time when a project pays back on a discounted basis.
10. Which one of the following statements is correct?
- The payback period of a project will be longer than the discounted payback period.
- The internal rate of return can be reliably used for all independent projects.
- The internal rate of return is used to evaluate different sized projects.
- The internal rate of return should not be used to rank mutually exclusive projects.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub