You are working on a project of constructing a college building. Draw and provide any one example of the following precedence activities in this project. a. Finish-to-start relationship b. Start-to-start relationship c. Finish-to-finish relationship d. Start-to-finish relationship.
Q: You have just performed a PERT analysis and have found that more than one path through the project…
A: As a matter of course and by definition, an assignment with zero (0) slack is thought about a basic…
Q: (triple constraint)
A: TRIPLE CONSTRAINT
Q: Used : Call center optimization as project , please give Citation if possible are required to…
A: Project Title: Redesign and Implementation of Employee Onboarding Process Objective: Modernize and…
Q: Financing is needed to fund new equipment for the build sites. A) You are required to create a…
A: Business required regular maintenance and adoption of updated technology to cope up withthe problems…
Q: Incorporating flotation costs into the analysis of a project will : a. increase the initial cash…
A: Explanation : Flotation costs increase the initial outlay of money because the company must raise…
Q: For this assignment, you will design a risk management plan for a project titled “prolonged waiting…
A: Here, I will design a risk management plan for a project, The project title- "Prolonged Waiting…
Q: When is it MOST important that integration is performed? A At key interface points 60 217 B During…
A: Note: We'll answer the first question since the exact one wasn't specified. Please submit a new…
Q: Using your results from Problem 6,(a) Calculate the probability that the project will be completedin…
A: Project management is the process of overseeing a team's activities to complete all project…
Q: You are in charge of implementing the internal website your company will use to display its event…
A: A Composite organizational structure is a combination of various organizational structures within…
Q: You have a choice to manage one of three projects. You are familiar with the first project’s…
A: Choosing the right project to manage can feel like navigating a three-way junction, each path…
Q: d. normal, premature, perpetual, failed
A: d. normal, premature, perpetual, failed
Q: Part 2 after the photo: Once the initial meeting is conducted Brian can hire the contractors to…
A: 1. Generate a priority matrix for AET's system move. A priority matrix is a tool that is used to…
Q: Office Automation Inc., developed a proposal for implementing a software system that will…
A: The above-given question is to prepare the project schedule. A project schedule is a timeline that…
Q: d) You are required to propose one tool for ranking projects for assessing the balance of projects,…
A: Project portfolio management (PPM) is an approach for evaluating possible projects based on their…
Q: This exercise tests your ability to come up with a detailed and elaborate Business Case for a…
A: Project management is the process of leading the work of a team or a group to achieve goals and meet…
Q: The SDLC is an established methodology which aims to manage the complexity of large software…
A: The System Development Life Cycle (SDLC) is a structured methodology used in software development to…
Q: A project manager is in charge of a project, and while they agree that a 60-hour work week is…
A: According to the question, we need to select three project management tactics, these tactics are…
Q: You are managing a large construction project that’s been broken down into sub-projects (or phases).…
A: When you have a project that’s broken up into sub-projects or phases, it’s important that you…
Q: Office Automation Inc., developed a proposal for implementing a software system that will…
A: A network diagram is a graphical representation of a project which helps to identify the activity…
Q: Suppose you are a senior project manager and five employees work under your supervision. Your team…
A: Decision making is the way toward settling on decisions by recognizing a choice, gathering data, and…
Q: Mangement Project management is a discipline that involves planning, organizing, and overseeing…
A: The given information explains the basic ideas of project management, which is a methodical way of…
Q: You are in charge of a project at the local community center. The center needs to remodel one of the…
A: A network diagram is a graphical representation of project that helps to identify the activity…
Q: when discussing processes related to Project Execution, the ISO 10006 stabdard splits this category…
A: The objective of the question is to identify which of the given options is not a subcategory of the…
Q: Office Automation Inc., developed a proposal for implementing a software system that will…
A: NOTE: We are allowed to do first 3 sub-parts only. In project management, a critical path is the…
Q: A) Using a hypothetical project in the mentioned company, prepare a Work Breakdown Structure for…
A: Here, the project is about implementing a new customer relationship management system, The final…
Q: The client of a project has requested the project team to crash 8 hours of time. The table below…
A: The network diagram for the above network is as below. I have used principles of AON network…
Q: John, Jack and Jill are project managers for Jusco Company. All three of them lead their own team,…
A: Efficiency and Effectiveness are not similar to each other. The term efficiency refers to completing…
Q: 1. Relate the project management lifecycle to the application development of a house cleaning…
A: Project management is the act of arranging, organizing, and watching how a project goes from…
Q: Which of the following in the project management process defines a set of clear, discrete set of…
A: While carrying out a particular project it is essential to develop some clarity on how the different…
Q: The ideal outcome of the planning process group is to complete a project successfully by delivering…
A: The ideal outcome of the planning process group is to complete a project successfully by delivering…
Q: In the space provided below create the network diagram that shows the relationship (logic) of…
A: The data given is shown below in a tabular form.
Q: (a). Develop a project network. (b) Develop an activity schedule. Activity Earliest Start Latest…
A: NOTE: We are allowed to do the first three sub-parts only. A project schedule with early and late…
Q: Constraints are those factors that can limit a project. Which of the following are considered…
A: Project management is the management that requires a unique type of skills processes resources and…
Q: Define Project Integration Management and the key components that make up Project Integration…
A: Project integration management is the coordination of all components of a task. This incorporates…
Q: c. What is the expected project completion time? Note: Do not round intermediate calculations. Round…
A: ActivityImmediate predecessorsTime (days)(a)(m)(b)A-159B-123CA357DA1410EB123FC, D1212GD, E168HF,…
Q: Office Automation Inc., developed a proposal for implementing a software system that will…
A: The objective of the question is to develop an activity schedule for the project, identify the…
Q: d) Assume that the company wants to complete the project in six months or 26 weeks. What is the…
A: Using the normal data for each activity, I would draw the network diagram, First, I would determine…
Q: A project has three tasks and three members. These tasks include preparing a bill of materials task…
A: An easy-to-use tool for defining project roles and responsibilities is the RACI matrix, which offers…
Q: The client of a project has requested the project team to crash 8 hours of time. The table below…
A: Crashing a project is a method used in project management that involves shortening the amount of…
![You are working on a project of constructing a college building. Draw and provide any one
example of the following precedence activities in this project.
a. Finish-to-start relationship
b. Start-to-start relationship
c. Finish-to-finish relationship
d. Start-to-finish relationship.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F8ba0cdde-eac9-487b-a25b-2c52e31b151c%2F925f7ee7-8434-4689-8670-949dae4acfe0%2Ffuo1pwy.jpeg&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
- The ideal outcome of the planning process group is to complete a project successfully by delivering the agreed-upon project scope within time, cost, and quality constraints Select one: True False Initiating involves developing a project charter, which is part of the project ______ management knowledge area. Select one: a. scope b. risk c. communications d. integration Estimate activity resources output Select one: a. Activity list, activity attributes, milestone list, project management plan updates b. Project schedule network diagrams, project documents updates c. Activity resource requirements, resource breakdown structure, project documents updates d. Schedule management plan As time progresses, the scope of a project should become ... Select one: a. more clear and specific b. more vague c. more ambiguous d. more difficultWhen is it MOST important that integration is performed? A At key interface points 60 217 B During project executing C At the end of each project management process D During project planningYou are managing a large construction project that’s been broken down intosub-projects (or phases). Each of these sub-projects is scheduled to takebetween three and six months to complete. At the end of each sub-project,you plan to go through the closing processes and document lessons learned.Which of the following BEST describes what you must do at the beginning ofeach sub-project or phase?A. Develop the preliminary scope statement for the phaseB. Make sure you don’t involve the team, to avoid introducing too much projectmanagement overheadC. Use the Earned Value Technique to decide whether or not to finish the projectD. Release all resources from the project and contact sellers to renegotiate allcontracts
- The four types of project closures are: Group of answer choices a. finite, infinite, continuous, discrete b. crashed, finished, successful, unsuccessful c. none of these d. normal, premature, perpetual, failedIn the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event. 1. In a given project activities "A, B and C are initial activities that may begin at the same time 2. -----"D" cannot begin until "A" is complete. 3. ----- "B" must be complete before E can begin. 4. ----- "F" cannot start until "C" is finished. 5. ----- "G" cannot begin until "B" is finished. 6. ----- "G" and "D" must be done before "H" can begin. 7. ----- "I" cannot begin until "B" is finished. 8. ----- "J" can begin only after "F" and "I" are complete. 9. ----- Once "E" is complete, "K" can begin. 10. ---- The project will be finished when "H" "J" and "K" are complete.Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) = (e) Develop an activity schedule for the crashed project. Activity EarliestStart LatestStart…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…how do i find the slack? Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Which of the following in the project management process defines a set of clear, discrete set of activities and resources required to complete a project? O Project Initiation. Project Execution. O Project Monitoring and Control. Project Planning.
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)