You are the CM for ABC Construction company, and you are preparing a Status Report document for your upcoming owners' meeting. Your actual overall duration of your schedule is four months longer than the 28 months baselined. What is your Schedule Variance Index information you would include in your Status Report? O 0.14 O 7.00 O 0.67 O 0.64

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter14: Pricing General Expenses
Section: Chapter Questions
Problem 4RQ
icon
Related questions
Question
1
You are the CM for ABC Construction company, and you are preparing a Status Report document for your
upcoming owners' meeting. Your actual overall duration of your schedule is four months longer than the 28
months baselined. What is your Schedule Variance Index information you would include in your Status
Report?
O 0.14
O 7.00
O 0.67
O 0.64
Transcribed Image Text:You are the CM for ABC Construction company, and you are preparing a Status Report document for your upcoming owners' meeting. Your actual overall duration of your schedule is four months longer than the 28 months baselined. What is your Schedule Variance Index information you would include in your Status Report? O 0.14 O 7.00 O 0.67 O 0.64
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Sectioning basics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,