Windsor Manufacturing planned to use $90 of material per unit but actually used $88 of material per unit. The company planned to produce 1,500 units but actually produced 1,200 units. What is the sales-volume variance?

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 11EA: A manufacturer planned to use $78 of variable overhead per unit produced, but in the most recent...
icon
Related questions
Question

Need answer please

Windsor Manufacturing planned to use
$90 of material per unit but actually
used $88 of material per unit. The
company planned to produce 1,500
units but actually produced 1,200
units.
What is the sales-volume variance?
Transcribed Image Text:Windsor Manufacturing planned to use $90 of material per unit but actually used $88 of material per unit. The company planned to produce 1,500 units but actually produced 1,200 units. What is the sales-volume variance?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College