Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: Cost of new equipment and timbers $ 275,000 Working capital required $ 100,000 Annual net cash receipts $ 120,000 * Cost to construct new roads in year three $ 40,000 Salvage value of equipment in four years $ 65,000
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area:
Cost of new equipment and timbers | $ | 275,000 | |
Working capital required | $ | 100,000 | |
Annual net cash receipts | $ | 120,000 | * |
Cost to construct new roads in year three | $ | 40,000 | |
Salvage value of equipment in four years | $ | 65,000 | |
*Receipts from sales of ore, less out-of-pocket costs for salaries, utilities, insurance, and so forth.
The mineral deposit would be exhausted after four years of mining. At that point, the working capital would be released for reinvestment elsewhere. The company’s required
Click here to view Exhibit 12B-1 and Exhibit 12B-2, to determine the appropriate discount factor(s) using tables.
Required:
a. What is the
b. Should the project be accepted?