Which statement about allocation of risk regarding differing site conditions and bidding is not correct? A contractor bids higher for a project on which he assumes more risk regarding differing site conditions. Unit prices in a bid help to mitigate the risk of differing site conditions to an owner and a contractor. A contractor’s bid will be affected by the allocation of risk. Differing site conditions are typically less of a source of contention for cost-plus contracts than for lump-sum contracts. An owner should expect higher bids if he accepts more of the risk for himself regarding differing site conditions
Which statement about allocation of risk regarding differing site conditions and bidding is not correct? A contractor bids higher for a project on which he assumes more risk regarding differing site conditions. Unit prices in a bid help to mitigate the risk of differing site conditions to an owner and a contractor. A contractor’s bid will be affected by the allocation of risk. Differing site conditions are typically less of a source of contention for cost-plus contracts than for lump-sum contracts. An owner should expect higher bids if he accepts more of the risk for himself regarding differing site conditions
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Which statement about allocation of risk regarding differing site conditions and bidding is not correct?
A contractor bids higher for a project on which he assumes more risk regarding differing site conditions.
Unit prices in a bid help to mitigate the risk of differing site conditions to an owner and a contractor.
A contractor’s bid will be affected by the allocation of risk.
Differing site conditions are typically less of a source of contention for cost-plus contracts than for lump-sum contracts.
An owner should expect higher bids if he accepts more of the risk for himself regarding differing site conditions
Expert Solution
Step 1
Option A:
A contractor bids higher for a project on which he assumes more risk regarding differing site conditions.
Explanation:
A “differing site condition” is an unexplained, hidden, concealed, or latent physical condition found at a site that varies from the fairly expected conditions. You can actually touch physical conditions, including rock and earth, and not touch intangible conditions, such as labor, price, and materials. There are only two realistic ways for a contractor to deal with DSCs risk – either carry out elaborate pre-bid checks, which will be embodied in bids; or have a contingency in bids, which may lead to bankruptcy.
Hence this statement is correct and hence this is not the correct answer according to the question.
Trending now
This is a popular solution!
Step by step
Solved in 5 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.