Tiger Equipment Inc., a manufacturer of construction equipment, prepared the following factory overhead cost budget for the Welding Department for May of the current year. The company expected to operate the department at 100% of normal capacity of 8,400 hours.   TIGER EQUIPMENT INC. Factory Overhead Cost Budget-Welding Department For the Month Ended May 31 1 Variable costs:     2 Indirect factory wages $30,240.00   3 Power and light 20,160.00   4 Indirect materials 16,800.00   5 Total variable cost   $67,200.00 6 Fixed costs:     7 Supervisory salaries $20,000.00   8 Depreciation of plant and equipment 36,200.00   9 Insurance and property taxes 15,200.00   10 Total fixed cost   71,400.00 11 Total factory overhead cost   $138,600.00       During May, the department operated at 8,860 standard hours. The factory overhead costs incurred were indirect factory wages, $32,400; power and light, $21,000; indirect materials, $18,250; supervisory salaries, $20,000; depreciation of plant and equipment, $36,200; and insurance and property taxes, $15,200. Required:   Prepare a factory overhead cost variance report for May. To be useful for cost control, the budgeted amounts should be based on 8,860 hours. Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries. Enter all variances as positive amounts.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter4: Job Order Costing
Section: Chapter Questions
Problem 7EB: A company estimates its manufacturing overhead will be $840,000 for the next year. What is the...
icon
Related questions
icon
Concept explainers
Question
Tiger Equipment Inc., a manufacturer of construction equipment, prepared the following factory overhead cost budget for the Welding Department for May of the current year. The company expected to operate the department at 100% of normal capacity of 8,400 hours.
 
TIGER EQUIPMENT INC.
Factory Overhead Cost Budget-Welding Department
For the Month Ended May 31
1
Variable costs:
 
 
2
Indirect factory wages
$30,240.00
 
3
Power and light
20,160.00
 
4
Indirect materials
16,800.00
 
5
Total variable cost
 
$67,200.00
6
Fixed costs:
 
 
7
Supervisory salaries
$20,000.00
 
8
Depreciation of plant and equipment
36,200.00
 
9
Insurance and property taxes
15,200.00
 
10
Total fixed cost
 
71,400.00
11
Total factory overhead cost
 
$138,600.00
 
 
 
During May, the department operated at 8,860 standard hours. The factory overhead costs incurred were indirect factory wages, $32,400; power and light, $21,000; indirect materials, $18,250; supervisory salaries, $20,000; depreciation of plant and equipment, $36,200; and insurance and property taxes, $15,200.
Required:
  Prepare a factory overhead cost variance report for May. To be useful for cost control, the budgeted amounts should be based on 8,860 hours. Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries. Enter all variances as positive amounts.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

what is the Total factory overhead cost variance?

Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning

Expert Answers to Latest Homework Questions