Using a waste factor of 8 percent, determine the number of cubic yards of concrete needed to pour the foundation walls shown in the figures below. Select one: a. 90 CY b. 71.98 CY c. 83.75 CY d. 101.21 CY 12 REBAR OC BOTH AYS 28 28 S DOWELS 17 OC ALTERNATING DIRECTIONS REBAR SEACH CONT REBAR 40

icon
Related questions
Question
B5
Using a waste factor of 8 percent,
determine the number of cubic yards of
concrete needed to pour the foundation
walls shown in the figures below.
Select one:
а. 90 CY
b. 71.98 CY
С. 83.75 СY
d. 101.21 CY
40
12
4 REBARO 12
OC. BOTH WAYS
12
28
28
17'
45 DOWELS@ 12
O.C. ALTERNATING
DIRECTIONS -
A REBAR
SEACH 4
CONT. REBAR
40
Transcribed Image Text:Using a waste factor of 8 percent, determine the number of cubic yards of concrete needed to pour the foundation walls shown in the figures below. Select one: а. 90 CY b. 71.98 CY С. 83.75 СY d. 101.21 CY 40 12 4 REBARO 12 OC. BOTH WAYS 12 28 28 17' 45 DOWELS@ 12 O.C. ALTERNATING DIRECTIONS - A REBAR SEACH 4 CONT. REBAR 40
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer