To find the earned value (EV) of a project, the percentage of work complete is multiplied by the O cost variance (CV) planned value (PV) actual cost of work performed (ACWP) budget at completion (BAC)

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 24P
icon
Related questions
Question
To find the earned value (EV) of a project, the percentage of work complete is multiplied by the
cost variance (CV)
planned value (PV)
actual cost of work performed (ACWP)
budget at completion (BAC)
Transcribed Image Text:To find the earned value (EV) of a project, the percentage of work complete is multiplied by the cost variance (CV) planned value (PV) actual cost of work performed (ACWP) budget at completion (BAC)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Cost control
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning