The surveyor established the stadia interval factor of a theodolite by setting up the instrument 50 m from the leveling rod and taking the upper and lower stadia hair reading as 2.166 and 1.665, respectively. Afterwards, the theodolite was used to determine the horizontal and vertical distance of a control point to the contstruction site. The theodolite was set-up in the control point, and the following data was gathered: STA OBS A m Elevation of control point: Height of instrument (fr ground): Determine the following: Upper Middle (m) (m) 2.446 Lower Vertical (m) Angle (°) 1.650 1.650 b) Elevation of construction site 8.500 m 1.100 m Remarks 10.256 construction site a) Horizontal distance of control point to construction site

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
The surveyor established the stadia interval factor of a theodolite by setting up the instrument 50
m from the leveling rod and taking the upper and lower stadia hair reading as 2.166 and 1.665,
respectively. Afterwards, the theodolite was used to determine the horizontal and vertical distance
of a control point to the contstruction site. The theodolite was set-up in the control point, and the
following data was gathered:
STA OBS
3
A
Elevation of control point:
Height of instrument (fr ground):
Determine the following:
3
Upper Middle Lower Vertical
(m) (m) (m) Angle (°)
2.446
1.650 1.650 10.256 construction site
Remarks
8.500 m
1.100 m
b) Elevation of
construction site
a) Horizontal distance of control point to construction
site
Transcribed Image Text:The surveyor established the stadia interval factor of a theodolite by setting up the instrument 50 m from the leveling rod and taking the upper and lower stadia hair reading as 2.166 and 1.665, respectively. Afterwards, the theodolite was used to determine the horizontal and vertical distance of a control point to the contstruction site. The theodolite was set-up in the control point, and the following data was gathered: STA OBS 3 A Elevation of control point: Height of instrument (fr ground): Determine the following: 3 Upper Middle Lower Vertical (m) (m) (m) Angle (°) 2.446 1.650 1.650 10.256 construction site Remarks 8.500 m 1.100 m b) Elevation of construction site a) Horizontal distance of control point to construction site
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
State plane coordinate systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning