The standard cost card for one unit of a certain finished product shows the following: Standard Quantity or Standard Price or Hours Rate Direct materials 10 pounds $? per pound Direct Labor 2.5 hours $16 per hour Variable manufacturing 1.5 hours $10 per hour overhead If the total standard variable cost for one unit of finished product is $85, then the standard price per pound for direct materials is: A. $5.90 B. $1.74 C. $3.00 D. $4.60
The standard cost card for one unit of a certain finished product shows the following: Standard Quantity or Standard Price or Hours Rate Direct materials 10 pounds $? per pound Direct Labor 2.5 hours $16 per hour Variable manufacturing 1.5 hours $10 per hour overhead If the total standard variable cost for one unit of finished product is $85, then the standard price per pound for direct materials is: A. $5.90 B. $1.74 C. $3.00 D. $4.60
Chapter5: Process Costing
Section: Chapter Questions
Problem 1PB: The following product costs are available for Stellis Company on the production of erasers: direct...
Related questions
Question

Transcribed Image Text:The standard cost card for one unit of a certain finished product shows
the following:
Standard Quantity or Standard Price or
Hours
Rate
Direct materials
10 pounds
$? per pound
Direct Labor
2.5 hours
$16 per hour
Variable manufacturing
1.5 hours
$10 per hour
overhead
If the total standard variable cost for one unit of finished product is $85,
then the standard price per pound for direct materials is:
A. $5.90
B. $1.74
C. $3.00
D. $4.60
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College