Vidyadhar, Rodika, and Manoj write code for a system that requires 4 modules. Each module takes an exponential amount of time to complete with mean 3.0 days. Once a coder is finished with a module, he/she starts another, but only one coder can work on a module. Let {X(t), t >=0} be the CTMC describing the number of modules remaining to code.
Show the rate diagram for X
Show the Q matrix