The purpose of this question is to explore the concepts of team's velocity and project size. Consider three teams operating with the following velocities, Team (a) – 400 points per iteration Team (b) – 500 points per iteration Team ( c) – 900 points per iteration Each team operates with the following cadence, Team (a) – 2 weeks per iteration Team (b) – 5 weeks per iteration Team ( c) – 3 weeks per iteration We also have the system test team that needs to integrate and test the complete application and cannot test a part of it. Consider three projects with the following sizes in points, 3000, 6000, 9000. Question is which team should engage with which project? The goal is for all three teams to complete their respective projects at the same time, and hence to enable the system test to start verification without waiting for anyone? Team (a) should receive a project with 6000 points Team (b) should receive a project with 3000 points Team (c) should receive a project with 9000 points Team (a) should receive a project with 3000 points Team (b) should receive a project with 6000 points Team (c) should receive a project with 9000 points Team (a) should receive a project with 9000 points Team (b) should receive a project with 6000 points Team (c) should receive a project with 3000 points
The purpose of this question is to explore the concepts of team's velocity and project size. Consider three teams operating with the following velocities, Team (a) – 400 points per iteration Team (b) – 500 points per iteration Team ( c) – 900 points per iteration Each team operates with the following cadence, Team (a) – 2 weeks per iteration Team (b) – 5 weeks per iteration Team ( c) – 3 weeks per iteration We also have the system test team that needs to integrate and test the complete application and cannot test a part of it. Consider three projects with the following sizes in points, 3000, 6000, 9000. Question is which team should engage with which project? The goal is for all three teams to complete their respective projects at the same time, and hence to enable the system test to start verification without waiting for anyone? Team (a) should receive a project with 6000 points Team (b) should receive a project with 3000 points Team (c) should receive a project with 9000 points Team (a) should receive a project with 3000 points Team (b) should receive a project with 6000 points Team (c) should receive a project with 9000 points Team (a) should receive a project with 9000 points Team (b) should receive a project with 6000 points Team (c) should receive a project with 3000 points
Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
Related questions
Question
The purpose of this question is to explore the concepts of team's velocity and project size. Consider three teams operating with the following velocities,
- Team (a) – 400 points per iteration
- Team (b) – 500 points per iteration
- Team ( c) – 900 points per iteration
Each team operates with the following cadence,
- Team (a) – 2 weeks per iteration
- Team (b) – 5 weeks per iteration
- Team ( c) – 3 weeks per iteration
We also have the system test team that needs to integrate and test the complete application and cannot test a part of it.
Consider three projects with the following sizes in points,
- 3000,
- 6000,
- 9000.
Question is which team should engage with which project? The goal is for all three teams to complete their respective projects at the same time, and hence to enable the system test to start verification without waiting for anyone?
|
||
|
||
|
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education