The ordinates of a 6h-UH are given: A storm has three successive 6-h intervals of rainfall magnitude of 3.0, 5.0, and 4.0 cm, respectively. Assuming a φ-index of 0.20 cm/hr and a base flow of 30m3/s, determine the plot of the resulting hydrograph of flow. Hint: Note that the storms follow a certain sequence: The 3cm rain is followed by the 5cm rain and then the 4cm rain, all of which are 6 hours in duration. The ordinates of the 5-cm DRH are lagged by 6 hours and the 4-cm DRH is lagged by 12 hrs. Using the method of superposition, the ordinates of the resulting 12cm hydrograph is obtained by combining the ordinates of the 3 DRHs.
The ordinates of a 6h-UH are given: A storm has three successive 6-h intervals of rainfall magnitude of 3.0, 5.0, and 4.0 cm, respectively. Assuming a φ-index of 0.20 cm/hr and a base flow of 30m3/s, determine the plot of the resulting hydrograph of flow. Hint: Note that the storms follow a certain sequence: The 3cm rain is followed by the 5cm rain and then the 4cm rain, all of which are 6 hours in duration. The ordinates of the 5-cm DRH are lagged by 6 hours and the 4-cm DRH is lagged by 12 hrs. Using the method of superposition, the ordinates of the resulting 12cm hydrograph is obtained by combining the ordinates of the 3 DRHs.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
100%
The ordinates of a 6h-UH are given:
A storm has three successive 6-h intervals of rainfall magnitude of 3.0, 5.0, and 4.0 cm, respectively. Assuming a φ-index of 0.20 cm/hr and a base flow of 30m3/s, determine the plot of the resulting hydrograph of flow.
Hint: Note that the storms follow a certain sequence: The 3cm rain is followed by the 5cm rain and then the 4cm rain, all of which are 6 hours in duration. The ordinates of the 5-cm DRH are lagged by 6 hours and the 4-cm DRH is lagged by 12 hrs. Using the method of superposition, the ordinates of the resulting 12cm hydrograph is obtained by combining the ordinates of the 3 DRHs.

Transcribed Image Text:Time (h)
6-h UH
ordinates (m³/s)
3
150
250
450
12
600
18
800
24
700
30
600
36
450
42
320
48
200
54
100
60
50
66
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning