The optimistic, most likely and pessimistic times of all activities of a project are given in che table below: Optimistic Time Most Likely Pessimistic Time Activity Time 1-2 1-3 5 6. 7 7 1-4 2-5 3-5 4-6 4 12 6. 15 1 1 1 2 8 5-6 4 7 Using the information given in the table, answer the following questions: i. Draw the project network. Find the expected duration and variance of each activity. Calculate the early and late event times for each event and the expected project length. Compute the variance and standard deviations of the project length. What is the probability of that the project will be completed in 22 days? ii. iii. iv. v.

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
100%
The optimistic, most likely and pessimistic times of all activities of a project are given in
the table below:
Optimistic
Most Likely
Pessimistic
Time
Activity
Time
Time
1-2
5
6.
1-3
1
1
1-4
2
4
12
2-5
3-5
3
6.
15
1
1
1
4-6
2
8.
5-6
1
4
7
Using the information given in the table, answer the following questions:
i. Draw the project network.
ii.
Find the expected duration and variance of each activity.
Calculate the early and late event times for each event and the expected project length.
Compute the variance and standard deviations of the project length.
What is the probability of that the project will be completed in 22 days?
iii.
iv.
v.
Transcribed Image Text:The optimistic, most likely and pessimistic times of all activities of a project are given in the table below: Optimistic Most Likely Pessimistic Time Activity Time Time 1-2 5 6. 1-3 1 1 1-4 2 4 12 2-5 3-5 3 6. 15 1 1 1 4-6 2 8. 5-6 1 4 7 Using the information given in the table, answer the following questions: i. Draw the project network. ii. Find the expected duration and variance of each activity. Calculate the early and late event times for each event and the expected project length. Compute the variance and standard deviations of the project length. What is the probability of that the project will be completed in 22 days? iii. iv. v.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 5 images

Blurred answer
Knowledge Booster
Point Estimation, Limit Theorems, Approximations, and Bounds
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman