The Oakleigh Company has the information available for its production facility for the month of July. The budgeted activity level for fixed manufacturing overhead was estimated to be 48 000 machine hours for the production cycle. Actual machine hours for the period were 50 000, which resulted in the completion of 9900 units. Materials purchased (21 000 items) $819 000 Material quantity variance $39 600 U Actual labour cost (15 000 hours) $102 000 Machine hours used 50 000 Variable overhead spending variance $2 500 U Actual fixed manufacturing overhead $150 000 Oakleigh's standard costs per unit are as follows: Direct materials Direct labour Variable overhead (applied on machine hours basis) 20 components @ $4 per item 1.5 hours @$6 per hour 4.8 hours @$2.5 per hour Fixed overhead (applied on machine 4.8 hours @ $3 per hour hour basis) a) calculate variable overhead efficiency variance b) calculate Fixed overhead budget variance c) calculate fixed overhead volume variance
The Oakleigh Company has the information available for its production facility for the month of July. The budgeted activity level for fixed manufacturing overhead was estimated to be 48 000 machine hours for the production cycle. Actual machine hours for the period were 50 000, which resulted in the completion of 9900 units. Materials purchased (21 000 items) $819 000 Material quantity variance $39 600 U Actual labour cost (15 000 hours) $102 000 Machine hours used 50 000 Variable overhead spending variance $2 500 U Actual fixed manufacturing overhead $150 000 Oakleigh's standard costs per unit are as follows: Direct materials Direct labour Variable overhead (applied on machine hours basis) 20 components @ $4 per item 1.5 hours @$6 per hour 4.8 hours @$2.5 per hour Fixed overhead (applied on machine 4.8 hours @ $3 per hour hour basis) a) calculate variable overhead efficiency variance b) calculate Fixed overhead budget variance c) calculate fixed overhead volume variance
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Concept explainers
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Topic Video
Question
Please do not give solution in image format thanku
![The Oakleigh Company has the information available for its production facility
for the month of July. The budgeted activity level for fixed manufacturing
overhead was estimated to be 48 000 machine hours for the production
cycle. Actual machine hours for the period were 50 000, which resulted in
the completion of 9900 units.
Materials purchased (21 000 items) $819 000
Material quantity variance
$39 600 U
Actual labour cost (15 000 hours)
$102 000
Machine hours used
50 000
Variable overhead spending variance $2 500 U
Actual fixed manufacturing overhead $150 000
Oakleigh's standard costs per unit are as follows:
Direct materials
Direct labour
Variable overhead (applied on
machine hours basis)
20 components @ $4 per item
1.5 hours @$6 per hour
4.8 hours @$2.5 per hour
Fixed overhead (applied on machine 4.8 hours @ $3 per hour
hour basis)
a) calculate variable overhead
efficiency variance
b) calculate Fixed overhead budget
variance
c) calculate fixed overhead volume
variance](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fd1d72d43-8fd3-48f1-9340-d9c28bf273d7%2F8c2bc0ad-00d5-4859-b54a-659a65746d9b%2Fm0llcid_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The Oakleigh Company has the information available for its production facility
for the month of July. The budgeted activity level for fixed manufacturing
overhead was estimated to be 48 000 machine hours for the production
cycle. Actual machine hours for the period were 50 000, which resulted in
the completion of 9900 units.
Materials purchased (21 000 items) $819 000
Material quantity variance
$39 600 U
Actual labour cost (15 000 hours)
$102 000
Machine hours used
50 000
Variable overhead spending variance $2 500 U
Actual fixed manufacturing overhead $150 000
Oakleigh's standard costs per unit are as follows:
Direct materials
Direct labour
Variable overhead (applied on
machine hours basis)
20 components @ $4 per item
1.5 hours @$6 per hour
4.8 hours @$2.5 per hour
Fixed overhead (applied on machine 4.8 hours @ $3 per hour
hour basis)
a) calculate variable overhead
efficiency variance
b) calculate Fixed overhead budget
variance
c) calculate fixed overhead volume
variance
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education