The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item End L C K B J G H Lead Time 2 2 3 3 2 3 2 Additional units Amount on Hand 0 11 15 20 25 Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) < Prev 34 3 0 Direct Components L(2), C(1), K(3) B(2), J(3) G(2), B(2) H(4), B(2) b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on The latest week 4 of 5 ⠀⠀⠀ Nevt b. An order for the end item is scheduled to be shipped at the start of week 1 What is the latest week that the order can be started and still be ready to ship time? (Hint. You don't need to develop an MRP plan.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The following table lists the components needed to assemble an end item, lead
times (in weeks), and quantities on hand.
Item
End
L
C
K
B
J
G
H
Lead Time
2
2
3
3
2
3
2
Additional units
Click here for the Excel Data File
a. If 43 units of the end item are to be assembled, how many additional units of
B are needed? (Hint: You don't need to develop an MRP plan.)
Amount
on Hand
0
11
15
20
25
34
3
0
< Prev
b. An order for the end item is scheduled to be shipped at the start of week 11.
What is the latest week that the order can be started and still be ready to ship on
Direct Components
L(2), C(1), K(3)
B(2), J(3)
G(2), B(2)
H(4), B(2)
The latest week
4 of 5
Navi
b. An order for the end item is scheduled to be shipped at the start of week 11.
What is the latest week that the order can be started and still be ready to ship on
time? (Hint. You don't need to develop an MRP plan.)
Transcribed Image Text:The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item End L C K B J G H Lead Time 2 2 3 3 2 3 2 Additional units Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don't need to develop an MRP plan.) Amount on Hand 0 11 15 20 25 34 3 0 < Prev b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on Direct Components L(2), C(1), K(3) B(2), J(3) G(2), B(2) H(4), B(2) The latest week 4 of 5 Navi b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint. You don't need to develop an MRP plan.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.