The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 11 minutes. Activity Activity Description Performance Time (mins) Predecessors A Attach wheels to tub 5.0 − B Attach motor to lid 1.5 − C Attach battery pack 2.8 B D Attach safety cutoff 4.0 C E Attach filters 3.0 B F Attach lid to tub 2.0 A, E G Assemble attachments 3.0 − H Function test 3.7 D, F, G I Final inspection 2.0 H J Packing 2.0 I a-b) One of the possible assignment of tasks to workstations is shown correctly in Fig. 2 . The efficiency of the assembly line with 3 workstations = 98.6498.64% (enter your response rounded to two decimal places). c) The goal is to have 100% efficiency. Is this possible? No d) The theoretical minimum number of workstations=33 (round your response up to the next whole number). How did they get these answers?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Activity
|
Activity Description
|
Performance Time (mins)
|
Predecessors
|
|
A
|
Attach wheels to tub
|
5.0
|
|
−
|
B
|
Attach motor to lid
|
1.5
|
|
−
|
C
|
Attach battery pack
|
2.8
|
|
B
|
D
|
Attach safety cutoff
|
4.0
|
|
C
|
E
|
Attach filters
|
3.0
|
|
B
|
F
|
Attach lid to tub
|
2.0
|
|
A, E
|
G
|
Assemble attachments
|
3.0
|
|
−
|
H
|
Function test
|
3.7
|
|
D, F, G
|
I
|
Final inspection
|
2.0
|
|
H
|
J
|
Packing
|
2.0
|
|
I
|