The following information is used for the question below. HakardPewlitt is producing a new model of laser printer, the Id10t. A year after the Id10t had been released, you have been given data on how well your workforce is producing. After looking at the numbers, you decide that you should figure out the variances in relation to your production team. The standard labour cost is $13.75 after pay, taxes, and benefits. You were surprised to see that the actual rate turned out to be $14.50. The actual number of hours your employees worked was 7800, but you know that the standard for the level of production (650 casings) is 7500 hours. Labour Efficiency Variance is: $4 125 Unfavourable $4 125 Favourable $4 125 $4 125
Q: I keep getting this question wrong and trying to see how to work it
A: Production costs are such cost of a company which the company must be incurred for the manufacturing…
Q: After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's…
A: Activity Based Costing (ABC Costing)Under the ABC Costing overheads are allocated on the basis of…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Spending Variance :— It is the difference between flexible budget and actual results. Flexible…
Q: After doing an account analysis of cost estimation and giving the results to your boss, you…
A: An ethical dilemma is a situation where a person faces a difficult choice between two or more…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Variances are the differences between the actual values and budgeted values. If the budgeted values…
Q: For years, Mattoon Components Company has used an actual plantwide overhead rate and based its…
A: Variable cost per unit=Total manufacturing overhead 2017-Total manufacturing overhead 2016Direct…
Q: 1. Prepare a flexible budget for March. 2. Prepare a report showing the spending variances for…
A: 1) FAB Corporation Flexible Budget For the Month Ended March 31 Machine-hours…
Q: explain why if a performance measure in the customer perspective of the balncef scorecard was…
A: A balanced scorecard refers to the management system that uses 4 perspectives to measure a company's…
Q: Casting production Total Cost per hour Selling price per per hour casting 100 $20.00 200 $17.00 300…
A: The process of the combination of various inputs being material along with the inputs which are…
Q: Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the…
A: Activity-Based Costing (ABC) is a costing methodology that assigns overhead costs to specific…
Q: When Jasmine realized how small the margin was for her main product, she was aghast. She knew the…
A: Manufacturing overhead is the cost which is incurred on the making of the goods. It includes costs…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: The variance is the difference between the actual data and standard output of the production. The…
Q: e president has asked that you review the company’s costing system and “do what you can to help us…
A: Solution: Activity variances are based on Budgeted amount at planned level and budgeted amounts at…
Q: Clason, Inc. manufactures door panels. Suppose clason is considering sending the following amounts…
A: Cost of new quality program = 68000 + 27000+ 39000 +58000 = $ 192000 Cost of old program = 86000+…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Activity variance is caused by the difference between planning level of activity and actual level of…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Solution:-The said question is asking to calculate the activity variances for March for FAB…
Q: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March.…
A: The variance is the difference between the actual data and standard output of the production. The…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Based on the given information Activity and Spending Variances are calculated belowExplanation:FAB…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Lets understand the basics.The variance is the difference between the actual data and standard…
Q: He has spent the last month working with employees in the plant to change over the machines more…
A: Activity Based Costing (ABC Costing)Under the ABC Costing overheads are allocated on the basis of…
Q: Bellingham Company produces a product that requires 3 standard direct labor hours per unit at a…
A: Labor rate variance = (Actual rate per hour - Standard rate per hour)*Actual hours workedLabor time…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Variances are the differences between the actual values and budgeted values. If the budgeted values…
Q: Malone Manufacturing p
A: Contribution margin is the difference between Sales Price and Variable Cost of the…
Q: Waterfun Technology produces engines for recreational boats. Because of competitive pressures, the…
A: 1. Receiving costs are to be considered as the value-added activities because both these are the…
Q: e just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door ope The…
A: Activity variances are based on Budgeted amounts at the planned level and budgeted amounts at the…
Q: Unique Inc. produces brakes for the Jeep Car Company. At the beginning of the year, they had the…
A: Labour cost variance is one of variance used in business in order to analyse differences in actual…
Q: Carpenter Company uses standard costing. The company has a manufacturing plant in Georgia. Standard…
A: Standard cost system: Standard cost system to the accounting systems which use standards for product…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Flexible budget is prepared to determine the budgeted cost to be incurred for the completion of a…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Variances is the amount of difference between the actual values and the values estimated by the…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Depreciation is the decrement in the value of tangible assets by the wear and tear during the…
Q: Fiske Corporation manufactures a popular regional brand of kitchen utensils. The design and variety…
A: The high-low method is used to differentiate the mixed costs. Mixed cost is the combination of fixed…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: Flexible budget is the statement which is prepared by the entity to estimate the fixed and the…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: The variance is the difference between the standard and actual cost data. The variance can be…
Q: of a revolutionary new garage door opening device. The president has asked that you review the…
A: The activity variance is the difference between flexible and master budget. The spending variance…
Q: Fiske Corporation manufactures a popular regional brand of kitchen utensils. The design and variety…
A: Variable cost Depends upon the production of goods or services that is increment of sales increases…
Q: Compute the amount of overhead allocated to the Sport and the Pro drones for the first quarter using…
A: ABC seems to be a costing approach that identifies activities in an organization and allocates the…
Q: fter much effort and analysis, you determined the following cost formulas and gathered the following…
A: 1. Activity Variances - Fab Corporation For the month ended March 31 Particulars Flexible…
Q: Unique Inc. produces brakes for the Jeep Car Company. At the beginning of the year, they had the…
A: To get the Direct Labour Rate Variance, we will compute it using the formula as follows: Direct…
Q: You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door…
A: A master budget can be defined as an estimate of the revenue earned or expenses incurred over a…
Q: Fiske Corporation manufactures a popular regional brand of kitchen utensils. The design and variety…
A: Variable costs are costs that vary with the change in the level of output whereas fixed costs are…
Q: Carpenter Company uses standard costing. The company has a manufacturing plant in Georgia. Standard…
A: Standard cost system: Standard cost system to the accounting systems which use standards for the…
Q: Carpenter Company uses standard costing. The company has a manufacturing plant in Georgia. Standard…
A: Standard cost system: Standard cost system to the accounting systems which use standards for the…
Q: Danna Lumus, the marketing manager for a division that produces a variety of paper products, is…
A: For computing the sales volume for which the two processes are equally profitable, we need to…
Step by step
Solved in 2 steps
- Ryan: Kaylin, this also sounds good to me. Go ahead and include the carrying cost in your computation. To help in the analysis, Kaylin gathered the following data for LLHC for 2011: Tons sold: 10 Average cartons per shipment: 2 Average shipments per ton: 7 1)After receiving the analysis of LLHC, Ryan decided to expand the analysis to all products. He also had Kaylin reevaluate the way in which mill overhead was assigned to products. After the restructuring was completed, Ryan took the following actions: (a) the prices of most low-volume products were increased, (b) the prices of several high-volume products were decreased, and (c) some low-volume products were dropped. Explain why his strategy changed so dramatically.You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Actual Cost in March $ 21,520 Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $16,300 + $0.18 per machine-hour $38,300 + $1.80 per machine-hour $0.80 per machine-hour $94,700 + $1.70 per machine-hour $68,000 $ 66,300 $ 15,000 $ 127,900 $ 69,700 During March, the company worked 17,000 machine-hours and produced 11,000 units. The company had originally planned to work 19,000 machine-hours during March.…Chic Design is a manufacturer of large flower pots for urban settings. The company has these standards: (Click the icon to view the standards.) Last month, the company reported the following actual results for the production of 1,800 flower pots: (Click the icon to view the actual results.) (Click the icon to view related variances.) Assume the company uses a standard cost accounting system. Date Data table Direct materials (resin) Direct labor..... Accounts Requirement 1. Record Watermate's direct material and direct labor journal entries. (Record debits first, then credits. Exclude explanations from any journal entries. Abbreviations used: DM = Direct materials, DL = Direct labor) Let's start by recording the entry for the purchase of raw materials. Journal Entry Standard variable manufacturing overhead rate Budgeted fixed manufacturing overhead Standard fixed MOH rate Print Debit Done Credit 12 pounds per pot at a cost of $5.00 per pound 2.0 hours at a cost of $23.00 per hour .…
- Carpenter Company uses standard costing. The company has a manufacturing plant in Georgia. Standard labor-hours per unit are 0.50, and the variable overhead rate for the Georgia plant is $3.50 per direct labor-hour. Fixed overhead for the Georgia plant is budgeted at $1,800,000 for the year. Firm management has always used variance analysis as a performance measure for the plant. Tom Saban has just been hired as a new controller for Carpenter Company. Tom is good friends with the Georgia plant manager and wants him to get a favorable review. Tom decides to underestimate production, and budgets annual output of 1,200,000 units. His explanation for this is that the economy is slowing and sales are likely to decrease. At the end of the year, the plant reported the following actual results: output of 1,500,000 using 760,000 labor-hours in total, at a cost of $2,700,000 in variable overhead and $1,850,000 in fixed overhead. Q.Summarize the fixed overhead variance based on both the projected…The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures: Average per Month (in days) 1 2 3 4 Wait time per order before start of production Inspection time per unit Process time per unit Queue time per unit Move time per unit 9.0 11.5 12.0 14.0 0.8 0.7 0.7 0.7 2.1 2.0 1.9 1.8 2.8 4.4 6.0 7.0 0.3 0.4 0.4 0.5 Required: 1-a. Compute the throughput time for each month. 1-b. Compute the manufacturing cycle efficiency (MCE) for each month. 1-c. Compute the delivery cycle time for each month. 3-a. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using…You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president asked you to review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find the company has never used a flexible budget, and you suggest preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you estimated the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $16,200 + $0.17 per machine-hour $38,700 +$1.50 per machine-hour $0.70 per machine-hour $94,300 +$1.10 per machine-hour $68,100 Actual Cost in March $ 21,570 $ 64,000 $ 14,500 $ 118,300 $ 69,800 During March, the company worked 19,000 machine-hours and produced 13,000 units. The company originally planned to work 21,000 machine-hours during March. Required: 1. Calculate…
- You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $16,800+ $0.12 per machine-hour $38,200+ $1.50 per machine-hour $0.70 per machine-hour $94,900 + $1.60 per machine-hour $67,500 Actual Cost in March $ 21,000 $ 62,000 $ 13,800 $ 127,800 $ 69,200 During March, the company worked 18,000 machine-hours and produced 12,000 units. The company had originally planned to work 20,000 machine-hours during March.…The information related to an assembly line process at a manufacturing company is shown in Figure Q2. Workstation D is the last work process with the process time of 30 sec/unit and 2% rejection rate. Other information related to the process is shown in the figure. The demand for the product is 37000 units per month. The company is operating for 24 days per month and 8 hours per day. (a) Evaluate the problem and determine the rate of components expected to be rejected from process C in units per hour. (b) Re-evaluate the overall problem and propose the number of machines required at workstation В. SS6 2% SS5 1% SS4 2% S7 SS3 SS2 S 5% 2% 3% 1 28 sec/unit 25 sec/unit A B D Output 5% 4% 3% 2% 131.7 39 sec/unit 30 sec/unit 103.4 sec/umt sec/unit Figure 2You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president asked you to review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find the company has never used a flexible budget, and you suggest preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you estimated the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $16,800 +$0.17 per machine-hour $38,500 +$1.50 per machine-hour $0.40 per machine-hour $94, 300 +$1.20 per machine-hour $67,800 Actual Cost in March $ 22,170 $ 63,800 $ 8,200 $ 120,400 $ 69,500 During March, the company worked 19,000 machine-hours and produced 13,000 units. The company originally planned to work 21,000 machine-hours during March. Required: 1. Calculate…
- You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $17,000+ $0.12 per machine-hour $38,300+ $1.70 per machine-hour $0.50 per machine-hour During March, the company worked 16,000 machine-hours and produced 10,000 units. The company had originally planned to work 18,000 machine-hours during March. Required: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March.…You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor. Depreciation Cost Formula $16,900 $0.14 per machine-hour $38, 300+ $1.30 per machine-hour $0.70 per machine-hour $94,700+ $1.50 per machine-hour $68, 100 Actual Cost in March $ 21,360 $ 56,800 $ 13, 100 $ 124, 100 $ 69,808 During March, the company worked 17,000 machine-hours and produced 11,000 units. The company had originally planned to work 19,000 machine-hours during…You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Cost Formula Actual Cost in March Utilities $16,800 + $0.21 per machine-hour $ 22,800 Maintenance $38,500 + $1.40 per machine-hour $ 60,300 Supplies $0.50 per machine-hour $ 9,800 Indirect labor $94,300 + $1.70 per machine-hour $ 129,200 Depreciation $68,000 $ 69,700 During March, the company worked 18,000 machine-hours and produced 12,000 units. The company had originally planned to work 20,000 machine-hours during…