The following data relate to the overhead expenditure of a contract cleaners at two activity levels. Square metres cleaned 13,500 15,950 Overheads $84,865 $97,850 What is the estimate of the overheads if 18,300 square metres are to be cleaned? A $96,990 B $110,305 C $112,267 D $115,039
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
The following data relate to the overhead expenditure of a contract cleaners at two activity levels.
Square metres cleaned 13,500 15,950
What is the estimate of the overheads if 18,300 square metres are to be cleaned?
A $96,990
B $110,305
C $112,267
D $115,039