18. Production overheads allocated and apportioned to cost centres in a factory for a period, along with additional data, are: Allocated overheads Apportioned overheads Additional data: Number of employees Direct labour hours Machine hours Production Cost Centre A B $17,628 $38,490 $29,938 $45,841 14 5,200 1,400 21 2,170 7,460 Service Cost Centre X $3,795 $4,640 C $14,671 $28,360 14 4,780 580 Y $6,130 $5,750 8

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Topic Video
Question
18.
Production overheads allocated and apportioned to cost centres in a factory for a
period, along with additional data, are:
Allocated overheads
Apportioned overheads
Additional data:
Number of employees
Direct labour hours
Machine hours
Production Cost Centre -
B
A
$17,628 $38,490-
$29,938
$45,841
(a)
(b)
14
5,200
1,400
21
2,170
7,460
C
$14,671
$28,360
14
4,780
580
Page
Service Cost Centre
X
$3,795
$4,640
7
Y
$6,130
$5,750
8
Overheads allocated and apportioned to Service Cost Centre X are re-apportioned on
the following basis: Production Cost Centre A 20%, Production Cost Centre B 45%,
Production Cost Centre C 35%.
Overheads allocated and apportioned to Service Cost Centre Y are re-apportioned on
the basis of the number of employees in the other cost centres.
Required:
Re-apportion the service cost centre overheads.
Calculate an overhead absorption rate for each production cost centre.
8
of 9
Transcribed Image Text:18. Production overheads allocated and apportioned to cost centres in a factory for a period, along with additional data, are: Allocated overheads Apportioned overheads Additional data: Number of employees Direct labour hours Machine hours Production Cost Centre - B A $17,628 $38,490- $29,938 $45,841 (a) (b) 14 5,200 1,400 21 2,170 7,460 C $14,671 $28,360 14 4,780 580 Page Service Cost Centre X $3,795 $4,640 7 Y $6,130 $5,750 8 Overheads allocated and apportioned to Service Cost Centre X are re-apportioned on the following basis: Production Cost Centre A 20%, Production Cost Centre B 45%, Production Cost Centre C 35%. Overheads allocated and apportioned to Service Cost Centre Y are re-apportioned on the basis of the number of employees in the other cost centres. Required: Re-apportion the service cost centre overheads. Calculate an overhead absorption rate for each production cost centre. 8 of 9
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education