The following data is given for the Walker Company: Budgeted production...............................................1,000 units Actual production........................................................980 units Materials: Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000 Labor: Standard hourly labor
Master Budget
A master budget can be defined as an estimation of the revenue earned or expenses incurred over a specified period of time in the future and it is generally prepared on a periodic basis which can be either monthly, quarterly, half-yearly, or annually. It helps a business, an organization, or even an individual to manage the money effectively. A budget also helps in monitoring the performance of the people in the organization and helps in better decision-making.
Sales Budget and Selling
A budget is a financial plan designed by an undertaking for a definite period in future which acts as a major contributor towards enhancing the financial success of the business undertaking. The budget generally takes into account both current and future income and expenses.
Use the following for the next five questions:
The following data is given for the Walker Company:
Budgeted production...............................................1,000 units
Actual production........................................................980 units
Materials:
Standard price per lb.......................................................$2.00
Standard pounds per completed unit....................................12
Actual pounds purchased and used in production.........11,800
Actual price paid for materials......................................$23,000
Labor:
Standard hourly labor rate....................................$14 per hour
Standard hours allowed per completed unit.........................4.5
Actual labor hours worked................................................4,560
Actual total labor costs..................................................$62,928
The direct labor effeciency variance is:
-
$912 F
-
-
-