The figure below shows the arrow diagram of the major events (A, B, D, E, F, G, H, I) of project, where each of them has the three estimates of duration (optimistic OP, most likely ML, pessimistic PE). Plan the project using PERT method and then answer the following questions: C(6,4,8) 3 I(2,5,8) G F \(1,2,3) 4,7,7) D B(6,5,7) (1,5,6) A E 2 (1,2,3) H (3,5,7) (2,4,6) 1) Indentify the critical path of network diagram and the mean time for the total duration of the project implementation. 2) Calculate the variance and the standard deviation of the mean time for the total duration of the project implementation. 3) What is the optimistic estimate and pessimistic estimate for the total duration of the project implementation.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Q/ The figure below shows the arrow diagram of the major events (A, B, C, D, E, F, G,
H, I) of project, where each of them has the three estimates of duration (optimistic
OP, most likely ML, pessimistic PE). Plan the project using PERT method and
then answer the following questions:
C(6,4,8),
3
I(2,5,8)
\G
F
\(1,2,3)
4,7,7)\
D
B(6,5,7) (1,5,6)
A
E
H
2
(1,2,3)
5.
(3,5,7)
(2,4,6)
1) Indentify the critical path of network diagram and the mean time for the total
duration of the project implementation.
2) Calculate the variance and the standard deviation of the mean time for the total
duration of the project implementation.
3) What is the optimistic estimate and pessimistic estimate for the total duration of
the project implementation.
Transcribed Image Text:Q/ The figure below shows the arrow diagram of the major events (A, B, C, D, E, F, G, H, I) of project, where each of them has the three estimates of duration (optimistic OP, most likely ML, pessimistic PE). Plan the project using PERT method and then answer the following questions: C(6,4,8), 3 I(2,5,8) \G F \(1,2,3) 4,7,7)\ D B(6,5,7) (1,5,6) A E H 2 (1,2,3) 5. (3,5,7) (2,4,6) 1) Indentify the critical path of network diagram and the mean time for the total duration of the project implementation. 2) Calculate the variance and the standard deviation of the mean time for the total duration of the project implementation. 3) What is the optimistic estimate and pessimistic estimate for the total duration of the project implementation.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Methods to determine productivity
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning