The demand for subassembly Sis 130 units in week 7. Each unit of S requires 1 unit of T and Z units of U. Each unit of T requires t unit of V. 1 unit of W. and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z One firm manufactures all items It takes 2 weeks to make S. 1 week to make T, 2 weeks to make U. 1 week to make V, 3 weeks to make W. 2 weeks to make X. 2 weeks to make Y, and 2 weeks to make Z Cick the icon to view the product structure and the ime-phased product structure. In addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes These units are needed in week 6 Modify the gross material requirements plan to reflect this change (type 0f the input bax is not used) Lead Time (weeks) Week Item Gross req Order release 2 The product structure. The time-phased product structure. Level Q

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
100%
The demand for subassembly Sis 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V. 1 unit of W. and 2 units of X. Finally, each unit
of U requires 2 units of Y and 3 units of Z One firm manufactures all items It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U. 1 week to make V. 3 weeks to make W. 2
weeks to make X. 2 weeks to make Y, and 2 weeks to make Z
W Click the icon to view the product structure and the time-phased product structure.
In addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes These units are needed in week
6 Modify the gross material requirements plan to reflect this change (type 0f the input bax is nat used)
Lead Time
(weeks)
Week
Item
Gross req
Order release
The product structure.
The time-phased product structure.
Level
Q
V
W
U/2)
X
Y
2 V(1) W1) X2) Y(2) Z3)
4
6.
Time in weeks
-co
Transcribed Image Text:The demand for subassembly Sis 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V. 1 unit of W. and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z One firm manufactures all items It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U. 1 week to make V. 3 weeks to make W. 2 weeks to make X. 2 weeks to make Y, and 2 weeks to make Z W Click the icon to view the product structure and the time-phased product structure. In addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes These units are needed in week 6 Modify the gross material requirements plan to reflect this change (type 0f the input bax is nat used) Lead Time (weeks) Week Item Gross req Order release The product structure. The time-phased product structure. Level Q V W U/2) X Y 2 V(1) W1) X2) Y(2) Z3) 4 6. Time in weeks -co
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Contemporary Marketing
Contemporary Marketing
Marketing
ISBN:
9780357033777
Author:
Louis E. Boone, David L. Kurtz
Publisher:
Cengage Learning
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L