The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. a) Choose the correct product structure. ○ A. Level 0 S 1 ○ C. U(2) 2 T (1) W (1) X(1) Y(1) Z(3) Level 0 S 1 T(1) 2 V(2) Y(1) Z (3) W (1) X (1) ☑ B. Level 0 S T(1) U(2) 1 2 V(2) W (1) X(1) Y(1) Z(3) → Level 0 S V(2) ☑ b) Choose the correct time-phased product structure. ○ A. B. Z V U Y W T ☑ Π ☑ S T W Y U Z ○ C. 1 2 Y(1) W (1) X (1) U(2) Z(3) V W T ☑ S Y U Z ☑ ☑ ○ D. W T ☑ S Y U Z 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 7 1 2 3 4 5 6 7 Time in weeks Time in weeks Time in weeks Time in weeks ☑

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question
100%
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit
of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1
week to make Z.
a) Choose the correct product structure.
○ A.
Level
0
S
1
○ C.
U(2)
2 T (1) W (1) X(1) Y(1) Z(3)
Level
0
S
1
T(1)
2 V(2) Y(1) Z (3) W (1) X (1)
☑
B.
Level
0
S
T(1)
U(2)
1
2 V(2)
W (1) X(1) Y(1) Z(3)
→
Level
0
S
V(2)
☑
b) Choose the correct time-phased product structure.
○ A.
B.
Z
V
U
Y
W
T
☑
Π
☑
S
T
W
Y
U
Z
○ C.
1
2 Y(1)
W (1) X (1)
U(2) Z(3)
V
W T
☑
S
Y
U
Z
☑
☑
○ D.
W T
☑
S
Y
U
Z
1 2 3 4 5 6 7
1
2 3 4 5
6
7
1 2 3 4 5
7
1 2 3 4 5 6
7
Time in weeks
Time in weeks
Time in weeks
Time in weeks
☑
Transcribed Image Text:The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. a) Choose the correct product structure. ○ A. Level 0 S 1 ○ C. U(2) 2 T (1) W (1) X(1) Y(1) Z(3) Level 0 S 1 T(1) 2 V(2) Y(1) Z (3) W (1) X (1) ☑ B. Level 0 S T(1) U(2) 1 2 V(2) W (1) X(1) Y(1) Z(3) → Level 0 S V(2) ☑ b) Choose the correct time-phased product structure. ○ A. B. Z V U Y W T ☑ Π ☑ S T W Y U Z ○ C. 1 2 Y(1) W (1) X (1) U(2) Z(3) V W T ☑ S Y U Z ☑ ☑ ○ D. W T ☑ S Y U Z 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 7 1 2 3 4 5 6 7 Time in weeks Time in weeks Time in weeks Time in weeks ☑
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,