The constraint at Rauchwerger Corporation is time on a particular machine. The company makes three products that use this machine. Data concerning those products appear below: WX KD FS Selling price per unit $ 335.15 $ 228.43 $ 199.18 Variable cost per unit $ 259.32 $ 173.14 $ 159.67 Minutes on the constraint 7.20 4.00 5.20 Assume that sufficient time is available on the constrained machine to satisfy demand for all but the least profitable product. Up to how much should the company be willing to pay to acquire more of the constrained resource? (Round your intermediate calculations to 2 decimal places.)
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
The constraint at Rauchwerger Corporation is time on a particular machine. The company makes three products that use this machine. Data concerning those products appear below:
WX | KD | FS | |
---|---|---|---|
Selling price per unit | $ 335.15 | $ 228.43 | $ 199.18 |
Variable cost per unit | $ 259.32 | $ 173.14 | $ 159.67 |
Minutes on the constraint | 7.20 | 4.00 | 5.20 |
Assume that sufficient time is available on the constrained machine to satisfy demand for all but the least profitable product. Up to how much should the company be willing to pay to acquire more of the constrained resource? (Round your intermediate calculations to 2 decimal places.)