The company incurred the following actual costs when it operated at 75% of capacity in October Direct materials (45,500 pounds @ $5.20 per pound) Direct labor (20,000 hours @ $12.20 per hour) $ 236,600 244,000 Overhead costs Indirect materials Indirect labor Power Maintenance Depreciation-Building Depreciation-Machinery Taxes and insurance Supervisory salaries Total costs $ 41,950 176,750 17,250 34,500 24,000 95,850 15,300 224,750 630,350 $ 1,110,950 Required: 1. Prepare flexible overhead budgets for October showing amounts of each variable and fixed cost at the 65%, 75%, and 85% capacit evels.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Topic Video
Question

Please do not give solution in image format thanku 

Antuan Company set the following standard costs per unit for its product.
Direct materials (3.0 pounds @ $5.00 per pound)
Direct labor (1.7 hours @ $12.00 per hour)
Overhead (1.7 hours @ $18.50 per hour)
Standard cost per unit
The standard overhead rate ($18.50 per direct labor hour) is based on a predicted activity level of 75% of the factory's
capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the 75% capacity
level
Overhead Budget (75% Capacity)
Variable overhead costs
Indirect materials
Indirect labor
Power
Maintenance
Total variable overhead costs
Fixed overhead costs
Depreciation Building
Depreciation Machinery
Taxes and insurance
Supervisory salaries:
Total fixed overhead costs
Total overhead costs
$ 15,000
75,000
15,000
30,000
135,000
24,000
71,000
$15.00
20.40
31,45
$66.85
17,000
224,750
336,750
$ 471,750
The company incurred the following actual costs when it operated at 75% of capacity in October
Transcribed Image Text:Antuan Company set the following standard costs per unit for its product. Direct materials (3.0 pounds @ $5.00 per pound) Direct labor (1.7 hours @ $12.00 per hour) Overhead (1.7 hours @ $18.50 per hour) Standard cost per unit The standard overhead rate ($18.50 per direct labor hour) is based on a predicted activity level of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the 75% capacity level Overhead Budget (75% Capacity) Variable overhead costs Indirect materials Indirect labor Power Maintenance Total variable overhead costs Fixed overhead costs Depreciation Building Depreciation Machinery Taxes and insurance Supervisory salaries: Total fixed overhead costs Total overhead costs $ 15,000 75,000 15,000 30,000 135,000 24,000 71,000 $15.00 20.40 31,45 $66.85 17,000 224,750 336,750 $ 471,750 The company incurred the following actual costs when it operated at 75% of capacity in October
The company incurred the following actual costs when it operated at 75% of capacity in October
Direct materials (45,500 pounds@ $5.20 per pound)
Direct labor (20,000 hours @ $12.20 per hour)
$236,600
244.000
Overhead costs
Indirect materials
Indirect labor
Power
Maintenance
Depreciation-Building
Depreciation Machinery
Taxes and insurance
Supervisory salaries
Total costs
For Month Ended October 31
Production (in units)
ANTUAN COMPANY
Flexible Overhead Budgets
$ 41,950
176,750
Required:
1. Prepare flexible overhead budgets for October showing amounts of each variable and fixed cost at the 65%, 75%, and 85% capacity
levels.
Variable Amount Total Fixed
per Unit
Cost
17,250
34,500
24,000
95,850
15,300
224,750
630.350
$ 1,110,950
Flexible Budget at Capacity Level of
65%
75%
85%
Transcribed Image Text:The company incurred the following actual costs when it operated at 75% of capacity in October Direct materials (45,500 pounds@ $5.20 per pound) Direct labor (20,000 hours @ $12.20 per hour) $236,600 244.000 Overhead costs Indirect materials Indirect labor Power Maintenance Depreciation-Building Depreciation Machinery Taxes and insurance Supervisory salaries Total costs For Month Ended October 31 Production (in units) ANTUAN COMPANY Flexible Overhead Budgets $ 41,950 176,750 Required: 1. Prepare flexible overhead budgets for October showing amounts of each variable and fixed cost at the 65%, 75%, and 85% capacity levels. Variable Amount Total Fixed per Unit Cost 17,250 34,500 24,000 95,850 15,300 224,750 630.350 $ 1,110,950 Flexible Budget at Capacity Level of 65% 75% 85%
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education