The city is installing a new swimming pool in the east end recreation centre. One design being considered is a reinforced concrete pool that will cost $5000000 to install. Thereafter, the inner surface of the pool will need to be refinished and painted every 10 years at a cost of $450000 per refinishing. Assuming that the pool will have essentially an infinite life, what is the present worth of the costs associated with the pool design? The city uses a MARR of 6%. Review the following table and calculate the present worth of the project for a +5% change in refinishing costs. Round your answer to the nearest dollar. Parameter Construction Costs Refinishing Costs MARR [%] -10% -5% Base Case +5% +10% $5000000 $450000 6 Present Worth of -10% -5% 0% +5% Costs +10% Changes to Construction Costs Changes to refinishing Costs Changes to MARR ????? ?
The city is installing a new swimming pool in the east end recreation centre. One design being considered is a reinforced concrete pool that will cost $5000000 to install. Thereafter, the inner surface of the pool will need to be refinished and painted every 10 years at a cost of $450000 per refinishing. Assuming that the pool will have essentially an infinite life, what is the present worth of the costs associated with the pool design? The city uses a MARR of 6%. Review the following table and calculate the present worth of the project for a +5% change in refinishing costs. Round your answer to the nearest dollar. Parameter Construction Costs Refinishing Costs MARR [%] -10% -5% Base Case +5% +10% $5000000 $450000 6 Present Worth of -10% -5% 0% +5% Costs +10% Changes to Construction Costs Changes to refinishing Costs Changes to MARR ????? ?
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
![The city is installing a new swimming pool in the east end recreation centre. One design being considered is a reinforced concrete pool that will cost $5000000 to install. Thereafter, the inner surface of the pool will
need to be refinished and painted every 10 years at a cost of $450000 per refinishing. Assuming that the pool will have essentially an infinite life, what is the present worth of the costs associated with the pool
design? The city uses a MARR of 6%.
Review the following table and calculate the present worth of the project for a +5% change in refinishing costs. Round your answer to the nearest dollar.
Parameter
Construction
Costs
Refinishing Costs
MARR [%]
-10%
-5%
Base Case +5%
+10%
$5000000
$450000
6
Present Worth of
-10%
-5%
0%
+5%
Costs
+10%
Changes to
Construction
Costs
Changes to
refinishing Costs
Changes to MARR
?????
?](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F784e96bd-d537-432c-83c6-73c364dfb1ee%2F9cf5572e-18e2-4281-8d24-d8fbb1b6b0ef%2Fqcktyrd_processed.png&w=3840&q=75)
Transcribed Image Text:The city is installing a new swimming pool in the east end recreation centre. One design being considered is a reinforced concrete pool that will cost $5000000 to install. Thereafter, the inner surface of the pool will
need to be refinished and painted every 10 years at a cost of $450000 per refinishing. Assuming that the pool will have essentially an infinite life, what is the present worth of the costs associated with the pool
design? The city uses a MARR of 6%.
Review the following table and calculate the present worth of the project for a +5% change in refinishing costs. Round your answer to the nearest dollar.
Parameter
Construction
Costs
Refinishing Costs
MARR [%]
-10%
-5%
Base Case +5%
+10%
$5000000
$450000
6
Present Worth of
-10%
-5%
0%
+5%
Costs
+10%
Changes to
Construction
Costs
Changes to
refinishing Costs
Changes to MARR
?????
?
AI-Generated Solution
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you


Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,

Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,


Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,

Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON

Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education