The board of directors of Oriole Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Oriole's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Oriole commenced doing business on January 1, 2023. 2. Construction activities for the year ended December 31, 2023, were as follows: Project Total Contract Price Billings through Cash collections 12/31/23 through 12/31/23 A $498,150 275,400 251,100 B 364,500 102,060 102,060 C 384,750 384,750 315,900 D 486,000 194,400 129,600 E 388,800 324,000 324,000 $2,122,200 $1,280,610 $1,122,660 Contract Costs Incurred Through Project 12/31/23 Estimated Additional Costs To Complete Contracts A $413,100 $97,200 B 94,770 221,130 C 283,500 -0- 299,700 234,900 E 259,200 64,800 $1,350,270 $618,030 3. Each contract is with a different customer. 4. Any work remaining to be done on the contracts is expected to be completed in 2024. Calculate the amount of gross profit (or loss) for the 2023 calendar year, which would be reported under the following methods. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Do not leave any answer field blank. Enter O for amounts.) The amount reported as gross profit (loss) under the completed-contract method for 2023 is: Projects A $ B C D E $ The amount reported as gross profit (loss) under the percentage-of-completion method (based on estimated costs) for 2023 is: Projects A $ B C D E $

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter12: Intangibles
Section: Chapter Questions
Problem 11P
icon
Related questions
Question
The board of directors of Oriole Construction Corp. is meeting to choose between the completed-contract method and the
percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been
engaged to assist Oriole's controller in the preparation of a presentation to be given at the board meeting. The controller provides
you with the following information:
1.
Oriole commenced doing business on January 1, 2023.
2. Construction activities for the year ended December 31, 2023, were as follows:
Project
Total
Contract Price
Billings through
Cash collections
12/31/23
through 12/31/23
A
$498,150
275,400
251,100
B
364,500
102,060
102,060
C
384,750
384,750
315,900
D
486,000
194,400
129,600
E
388,800
324,000
324,000
$2,122,200
$1,280,610
$1,122,660
Contract Costs
Incurred Through
Project
12/31/23
Estimated
Additional Costs
To Complete Contracts
A
$413,100
$97,200
B
94,770
221,130
C
283,500
-0-
299,700
234,900
E
259,200
64,800
$1,350,270
$618,030
3.
Each contract is with a different customer.
4.
Any work remaining to be done on the contracts is expected to be completed in 2024.
Transcribed Image Text:The board of directors of Oriole Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Oriole's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Oriole commenced doing business on January 1, 2023. 2. Construction activities for the year ended December 31, 2023, were as follows: Project Total Contract Price Billings through Cash collections 12/31/23 through 12/31/23 A $498,150 275,400 251,100 B 364,500 102,060 102,060 C 384,750 384,750 315,900 D 486,000 194,400 129,600 E 388,800 324,000 324,000 $2,122,200 $1,280,610 $1,122,660 Contract Costs Incurred Through Project 12/31/23 Estimated Additional Costs To Complete Contracts A $413,100 $97,200 B 94,770 221,130 C 283,500 -0- 299,700 234,900 E 259,200 64,800 $1,350,270 $618,030 3. Each contract is with a different customer. 4. Any work remaining to be done on the contracts is expected to be completed in 2024.
Calculate the amount of gross profit (or loss) for the 2023 calendar year, which would be reported under the following methods.
(Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Do not leave any answer
field blank. Enter O for amounts.)
The amount reported as gross profit (loss) under the completed-contract method for 2023 is:
Projects
A
$
B
C
D
E
$
The amount reported as gross profit (loss) under the percentage-of-completion method (based on estimated costs) for 2023 is:
Projects
A
$
B
C
D
E
$
Transcribed Image Text:Calculate the amount of gross profit (or loss) for the 2023 calendar year, which would be reported under the following methods. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Do not leave any answer field blank. Enter O for amounts.) The amount reported as gross profit (loss) under the completed-contract method for 2023 is: Projects A $ B C D E $ The amount reported as gross profit (loss) under the percentage-of-completion method (based on estimated costs) for 2023 is: Projects A $ B C D E $
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Cornerstones of Financial Accounting
Cornerstones of Financial Accounting
Accounting
ISBN:
9781337690881
Author:
Jay Rich, Jeff Jones
Publisher:
Cengage Learning