The activities of an IT project have the durations (in months) and dependencies as shown in Table1. Assume that the planned start date of the project is Sunday 1 August 2021. Activity Description Predecessor Duration in Months   Planning     A    Problem Definition - 1 B    Statement of Scope and Objectives - 1 C    Feasibility Study - 2   Analysis     D    ERD A, B, C 9 E    Context Diagram, and DFD A,B, C 6   Design     F    Physical Database Design D 3 G    Graphical User Interface F 6   Implementation     H    Implementation and S/W Testing F, G 15 I    Installing the network and Network Security H 3   Testing     J    System Acceptance Testing I 3 Table1 Draw a network diagram using Ms. Project Management or Project liber for this project showing on the diagram the duration of each activity, predecessor, the earliest start, earliest finish, latest start, and latest finish dates, the free float, and the total float. What is the expected total duration of the project?1840 What is the critical path? Display the critical path only in red color using the S/W. The critical path is the longest sequence of tasks that must be completed to successfully conclude a project, from start to finish. Insert the following human resources needed to implement the project as shown in table2. Human Resource Standard rate Overtime rate Project Manager (PM) $30/Hr $35/Hr Systems Analyst and Designer (SAAD) $22/Hr $27/Hr Web Designer (WD) $23/Hr $28/Hr Software Developer (SD) $20/Hr $25/Hr Database Administrator (DBA) $23/Hr $28/Hr Software Tester (ST) $21/Hr $26/Hr Network Specialist (NS) $21/Hr $26/Hr Network Security Specialist (NS) $23/Hr $28/Hr System Integrator (SI) $23/Hr $28/Hr Table2 Populate each task with the corresponding human resources who is going to be working on each task as shown in table3. Activity Description HR   Planning   A    Problem Definition PM B    Statement of Scope and Objectives PM and SAAD C    Feasibility Study PM   Analysis   D    ERD SAAD E    Context Diagram, and DFD SAAD   Design   F    Physical Database Design SAAD, and DBA G    Graphical User Interface SAAD, and WD   Implementation   H    Implementation and S/W Testing SD, and ST I    Installing the network and Network Security NS, and NSS   Testing   J    System Acceptance Testing SI, ST, and SD Table3 Calculate through the S/W the total required time, and the cost of every phase of the System Development Life Cycle (SDLC).

Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
icon
Related questions
Question

The activities of an IT project have the durations (in months) and dependencies as shown in Table1. Assume that the planned start date of the project is Sunday 1 August 2021.

Activity

Description

Predecessor

Duration in Months

 

Planning

 

 

A

   Problem Definition

-

1

B

   Statement of Scope and Objectives

-

1

C

   Feasibility Study

-

2

 

Analysis

 

 

D

   ERD

A, B, C

9

E

   Context Diagram, and DFD

A,B, C

6

 

Design

 

 

F

   Physical Database Design

D

3

G

   Graphical User Interface

F

6

 

Implementation

 

 

H

   Implementation and S/W Testing

F, G

15

I

   Installing the network and Network Security

H

3

 

Testing

 

 

J

   System Acceptance Testing

I

3

Table1

  1. Draw a network diagram using Ms. Project Management or Project liber for this project showing on the diagram the duration of each activity, predecessor, the earliest start, earliest finish, latest start, and latest finish dates, the free float, and the total float.
  2. What is the expected total duration of the project?1840
  3. What is the critical path? Display the critical path only in red color using the S/W.

The critical path is the longest sequence of tasks that must be completed to successfully conclude a project, from start to finish.

  1. Insert the following human resources needed to implement the project as shown in table2.

Human Resource

Standard rate

Overtime rate

Project Manager (PM)

$30/Hr

$35/Hr

Systems Analyst and Designer (SAAD)

$22/Hr

$27/Hr

Web Designer (WD)

$23/Hr

$28/Hr

Software Developer (SD)

$20/Hr

$25/Hr

Database Administrator (DBA)

$23/Hr

$28/Hr

Software Tester (ST)

$21/Hr

$26/Hr

Network Specialist (NS)

$21/Hr

$26/Hr

Network Security Specialist (NS)

$23/Hr

$28/Hr

System Integrator (SI)

$23/Hr

$28/Hr

Table2

  1. Populate each task with the corresponding human resources who is going to be working on each task as shown in table3.

Activity

Description

HR

 

Planning

 

A

   Problem Definition

PM

B

   Statement of Scope and Objectives

PM and SAAD

C

   Feasibility Study

PM

 

Analysis

 

D

   ERD

SAAD

E

   Context Diagram, and DFD

SAAD

 

Design

 

F

   Physical Database Design

SAAD, and DBA

G

   Graphical User Interface

SAAD, and WD

 

Implementation

 

H

   Implementation and S/W Testing

SD, and ST

I

   Installing the network and Network Security

NS, and NSS

 

Testing

 

J

   System Acceptance Testing

SI, ST, and SD

Table3

  1. Calculate through the S/W the total required time, and the cost of every phase of the System Development Life Cycle (SDLC).

 

Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY