Table below is a time-phased net requirements for Widgets over the next six weeks along with the capacity constraint. Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 Capacity 600 600 600 400 200 200 The setup cost is $200 and the holding cost is $0.30 per unit per week. Accounting for the capacity constraint, the modified requirements schedule, without improvement step, is: Note: Enter your answer as integer. Week Requirement, r' 1 2 3 4 5 16
Table below is a time-phased net requirements for Widgets over the next six weeks along with the capacity constraint. Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 Capacity 600 600 600 400 200 200 The setup cost is $200 and the holding cost is $0.30 per unit per week. Accounting for the capacity constraint, the modified requirements schedule, without improvement step, is: Note: Enter your answer as integer. Week Requirement, r' 1 2 3 4 5 16
Related questions
Question

Transcribed Image Text:Table below is a time-phased net requirements for
Widgets over the next six weeks along with the
capacity constraint.
Week
1 2 3 4 5 6
Requirements 335 200 140 440 300 200
Capacity
600 600 600 400 200 200
The setup cost is $200 and the holding cost is
$0.30 per unit per week.
Accounting for the capacity constraint, the
modified requirements schedule, without
improvement step, is:
Note: Enter your answer as integer.
Week Requirement, r'
1
2
3
4
5
16