Suppose your organization is deciding which of THREE projects to bid on. The information or each is in the Table 2 below. Assume that all up-front investments are not recovered, so the are shown as negative profits. Table 2: Three Projects Details Estimated Probability (P) Profits/Losses Project A 50% RM120,000 50% (RM50,000) Project B 30% RM100,000 40% RM50,000 30% (RM60,000) Project C 70% RM20,000 30% (RM5,000) Tasks: (a) Calculate the Expected Monetary Value (EMV) for each project. Then, insert all the detail: into the table. (b) Based on your result, explain on which projects you would bid. Be sure to use the EMV information and your personal risk tolerance to justify your answer.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Suppose your organization is deciding which of THREE projects to bid on. The information or
each is in the Table 2 below. Assume that all up-front investments are not recovered, so the
are shown as negative profits.
Table 2: Three Projects Details
Estimated
Probability (P)
Profits/Losses
Project A
50%
RM120,000
50%
(RM50,000)
Project B
30%
RM100,000
40%
RM50,000
30%
(RM60,000)
Project C
70%
RM20,000
30%
(RM5,000)
Tasks:
(a) Calculate the Expected Monetary Value (EMV) for each project. Then, insert all the detail:
into the table.
(b) Based on your result, explain on which projects you would bid. Be sure to use the EMV
information and your personal risk tolerance to justify your answer.
Transcribed Image Text:Suppose your organization is deciding which of THREE projects to bid on. The information or each is in the Table 2 below. Assume that all up-front investments are not recovered, so the are shown as negative profits. Table 2: Three Projects Details Estimated Probability (P) Profits/Losses Project A 50% RM120,000 50% (RM50,000) Project B 30% RM100,000 40% RM50,000 30% (RM60,000) Project C 70% RM20,000 30% (RM5,000) Tasks: (a) Calculate the Expected Monetary Value (EMV) for each project. Then, insert all the detail: into the table. (b) Based on your result, explain on which projects you would bid. Be sure to use the EMV information and your personal risk tolerance to justify your answer.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.