Suppose you are a project manager of a power plant project and there is a penalty in your contract with the main client for every day you deliver the project late. You need to decide which sub-contractor is appropriate for your projects critical path activities. But while selecting a sub-contractor, you should take into consideration the costs and delivery dates. • Sub-contractor A bids 200,000 OMR. You estimate that there is a 35% possibility of completing 50 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late. • Sub-contractor B bids 260,000 OMR. You estimate that there is a 13% possibility of completing 15 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late. Determine which sub-contractor is appropriate for your projects critical path activities. Both sub- contractors promise successful delivery and high-quality work.
Suppose you are a project manager of a power plant project and there is a penalty in your contract with the main client for every day you deliver the project late. You need to decide which sub-contractor is appropriate for your projects critical path activities. But while selecting a sub-contractor, you should take into consideration the costs and delivery dates.
• Sub-contractor A bids 200,000 OMR. You estimate that there is a 35% possibility of completing 50 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late.
• Sub-contractor B bids 260,000 OMR. You estimate that there is a 13% possibility of completing 15 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late.
Determine which sub-contractor is appropriate for your projects critical path activities. Both sub- contractors promise successful delivery and high-quality work.
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)